CITY OF PLYMOUTH ORDINANCE
ORDINANCE NUMBER 1396
APPENDIX A-1
PROCEDURE OUTLINE FOR DRAINAGE PLAN APPROVAL
(See Section 2 for detailed information)
Applicant may begin with step 1 or step 5.
- Submit preliminary plans and application
{21 days prior to Step 3}
- Review by City Sewer Superintendent
- Action by Sanitary Board of Trustees
A-1-1
- Conditional Approval:
{Go to Step 4 or 5} - Approval:
{Go to Step 4 or 5} - Disapproval:
{Go back to Step 1} - Refer to Sewer Superintendent:
{Go to Step 3}
- Grading and installation of drainage features
{Go to Step 5}
- Submit final plans and application
{21 days prior to Step 8}
- Review by City Sewer Superintendent
- Financial guarantees
- Action by Sanitary Board of Trustees
- Conditional Approval:
{Go to Step 9} - Approval:
{Go to Step 9} - Disapproval:
{Go back to Step 1} - Refer to Sewer Superintendent:
{Go to Step 8}
- Construction completed
- File completion affidavit and "As Built" plans
- Review for compliance by Sewer Superintendent
{30 days after Step 10}
- Bond termination {60 days after Step 10}
This outline is for guidance only and not a part of this Ordinance.
| 
PLYMOUTH CODE of ORDINANCES | visit www.amlegal.com to view codes will open in new window
|


2003 ELECTION RESULTS
 |