Mayor's Office

Clerk-Treasurer

Council

City Attorney

Human Resources

Police Department

Fire Chief / EMS

Street / Sanitation Departments

Cemetery

Public Works

Building Commissioner

Planning Consultant

Water Department

Wastewater Department

Wastewater
Pre-Treatment


Park & Recreation Department

Airport Manager

Humane Society

Other Committees


SANITARY BOARD OF TRUSTEES

Gary Cook Mayor
Toni L. Hutchings Clerk-Treasurer
Jack B. Greenlee Council - 4 year ending 12-31-07
Steve Benczik Trustee - 4 year ending 12-31-07
Donnie Davidson Superintendent
Dennis Hooker Coordinator


Meeting Schedule and Minutes
January 2007
Monday, January 8

Monday, Jaunary 22
February 2007
Monday, February 12
Monday, February 26
March 2007
Monday, March 14
Monday, March 28
April 2007
Monday, April 9

Monday, April 23
May 2007
Monday, May 14

Monday, May 28
June 2007
Monday, June 11
Monday, June 25
July 2007
Monday, July 9

Monday, July 23
August 2007
Monday, August 13

Monday, August 27
September 2007
Monday, September 10
Monday, September 24
October 2007
Monday, October 8

Monday, October 22
November 2007
Monday, November 12

Monday, November 26
December 2007
Monday, December 10
Final Meeting - TBD

Minutes

321
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JANUARY 9, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, January 9, 2006 immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:08 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski,  Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on December 26, 2005, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for December 2005:

Plant Operations:
1)   Total flow in gallons                                51,074,532
2)   Average daily flow in gallons                   1,647,566
3)   Monthly average in BOD removal                  99.1%
4)   Monthly average in TSS removal                   96.4%
5)   Monthly average in Ammonia removal         99.5%
6)   Completed facility inventory count for State Board of Accounts.
7)   Constructed fabrication area in warm barn, including safer welding area.
8)   Installed additional large equipment storage racks in warm barn.
9)   Completed locating wastewater utility using our "GPS - Locating Unit" on the east side of the city.

Meetings Attended
12/7/05         Two men received instructor training for CPR and First Aid.
12/12/05       Sanitary Board Meeting
12/14/05       Eleven employees attended the December meeting held in Nappanee by the Northern Indiana
                       Operators Association on Class A sludge treatment.
12/26/05       Sanitary Board Meeting
12/29/05       Two employees attended strategy meeting with Commonwealth Engineers in Indianapolis on
                       proposed alternatives for the City's submitted Combined Sewer Overflow - Long Term Control
                       Plan.

Collection System:
1) Cleaned 720 linear feet of sewer lines.
  • 720' during service calls
  • 0' during preventive maintenance
2) Televised 560 linear feet of sewer lines
3) Mechanically removed roots from zero linear feet of sewer lines.
4) Removed approximately 0 tons of silt and debris during cleaning and inspections of sanitary
    sewers.
5) Used approximately 1,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the
     submitted CSO-LTCP.

     Superintendent Davidson reported that he would be meeting with IDEM on Thursday in reference to the Combined Sewer Overflow Long Term Control Plan. Davidson said that he had received a  comment letter from IDEM on the plan they submitted. Davidson said that the due date for the city's response is the first part of February. IDEM is asking for particular informa'don on Phase II. Davidson said that IDEM has decided to follow the Michigan policy fairly closely, which has provided the city with more guidance as far as determining which storm event they are going to design for. Davidson said he and Commonwealth Engineers will present some alternatives to IDEM on Thursday.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for December 16-31, 2005 and the claims for January 9, 2006 as entered in Claim Register #2006. The motion carried.

     Trustees Benczik and Greenlee moved and seconded to set the second and fourth Monday of each month, immediately following the meeting of the Water Works Board of Trustees. The motion carried.

     Jerry Thompson, the now manager of Johnny on the Spot, addressed the board. He said that last fall one of the drivers left sewage on the ground at the wastewater treatment plant when he was dumping the contents of the truck. Thompson said that their rights to use the plant were revoked. He said that he understeod that the city had problems with a couple of other drivers also. Thompson said that in November

322
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JANUARY 9, 2006

they terminated all of their drivers and he is currently the only route driver. Thompson said he took over as manager January 1st and that previously drivers were not trained. Thompson said that he has developed a training policy and that the trucks have since been equipped with hoses. Thompson asked for permission for Johnny on the Spot to begin using the treatment plant again.

     Trustee Cook asked him to submit the request in writing.

     Superintendent Davidson said that there were several instances when problems occurred, plus there was a lack of communication at Blueberry Festival time. Davidson said that there were some assumptions made regarding discharging, delays in getting the discharge sheets to the wastewater treatment facility, and delays in payments. Davidson said that he thought they could work something out, but he wanted it clear that the wastewater treatment facility requires certain standards.
 
     Benczik verified with Davidson that the standards are in writing.

     Benczik asked Mr. Thompson to put the required standards in the letter that he is to submit, and state that they will adhere to those standards.

     Benczik asked if there is a contract that could be signed.

     Davidson said that vendors like Johnny on the Spot are required by IDEM to annually submit a letter from a municipality to discharge. Davidson said that they are given a set of guidelines to which they must adhere, or their privileges are revoked. Davidson said that they are required to complete a manifest on each load that they bring in. Davidson said that the loads are periodically sampled by the wastewater treatment facility. Davidson said that there was an accumulation of violations, so he revoked their privileges. At that time, Davidson said that he wrote a letter to Mr. White, the owner, and said that he would review it after the first of the year, but that they would need permission from the board to begin discharging at the Plymouth Wastewater Treatment Facility.

     The board commended Davidson for the awards recently received by the wastewater treatment facility from the Indiana Water Environment Federation. The awards include "Best Annual Report" and "Safety Excellence" for third class cities for 2005.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:17 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

323
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JANUARY 23, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, January 23, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:14 p.m.

     Mayor Gary Cook presided for Trustee Greenlee. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present. Trustee Benczik was absent.

     Trustees Cook and Greenlee moved and seconded to approve the minutes of the last regular meeting on January 9, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     A legal notice was advertised in the Pilot News on January 12, 2006 for a public hearing to be conducted by the Sanitary Board of Trustees to update the City of Plymouth Combined Sewer Overflow-Long Term Control Plan, Phase II.

     Mayor Cook made a motion to open the public hearing for the Combined Sewer Overflow Long Term Control Plan. Trustee Greenlee seconded the motion. Motion carried.

     Mark Sullivan, from Commonwealth Engineers, reviewed the Long Term Control Plan history including estimated Phase I project costs for 2002-2005. Sullivan said that for the past several years, the wastewater department has been separating sanitary and storm sewers. The department has also been looking for and repairing leaks where there is clear water is getting into the sanitary sewer. Sullivan complimented the wasteweter deparbrnent for being able to save money by being able to use department employees to make the repairs instead of having to contract the work out.

     Sullivan said that the state has now issued standards for the city to adopt and Commonwealth Engineers has entered that information into computer model of the cites sewer system, helping to determine the necessary steps for Phase II. Sullivan anticipated the construction costs to be approximately $1.5 million with a 10% contingency and non-construction costs of 25% for a total estimated project cost of $2.1 million. Sullivan said the state will probably issue a five-year time frame for Phase II.

     Davidson said that the City of Plymouth did not have a wastewater treatment facility until 1955. Sewers were starting to be installed in the late 1800s, collecting sanitary waste and storm water in one pipe and going to the river. Davidson explained that the department has been working to update and correct the system with minimal impact to the rate payers.

     Mayor Cook thanked Davidson and his staff for what they have done in-house to save money for the rate payers of the City of Plymouth.

     Trustees Cook and Greenlee moved and seconded to close the public hearing. Motion carried.

     Superintendent Davidson referred to the discussion at the January 9th meeting with the manager of Johnny on the Spot. Davidson reviewed the following letters:

     Johnny on the Spot
     5292 South State Road 10
     Knox, IN 46534
     (574)772-5424

     January 9, 2006

     Mr. Davidson:

     In regards to our discussion on January 9, 2006 at the meeting I am sending you this letter.

     I am requesting that we have the dumping privilege reinstated for Johnny On the Spot. I am sorry for past problems but I had no control of that situation. Now that I am manager, I can guarantee

324
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JANUARY 23, 2006

you that I will personally train all new employees. If you or your staff have any problems with any of our employees, please notify me and I will resolve it immediately.

     If you approve my request, I would appreciate it if you would send me a letter for IDEM. We need letters from all placers we dump. We passed our inspection on the 28th of December, but must send a letter from all of our dump stations to them.

     Sincerely,
     S/Jerry Thompson


     1-17-2006

     Jerry Thompson
     Johnny on the Spot
     5292 South State Road 10
     Knox, IN 46534

     Re: Portable Toilet Waste

     Dear Mr. Thompson,

     I have received and reviewed your request for reinstatement of discharge privileges at the City of Plymouth Wastewater Treatment Facility. Approval is granted beginning February 1, 2006. Please understand the following items will be addressed or a permanent ban on your company's discharge privileges will be implemented.

     1. Contact with the POTW prior to scheduled delivery to assure our facility is receiving waste that day.
     2. Accurate and legible manifests on each load.
     3. Training of each driver on the City of Plymouth's rules and procedures.
     4. Communication no later than August 15, 2006 on the status of the Blueberry Festival waste.
     5. Prompt delivery of manifests and payment.
     
     If you have any questions, contact me at (574)936-3017.

     Sincerely,
     S/Donnie Davidson, Superintendent
     City of Plymouth Wastewater Department

     Encl.: 2006 Holiday Ordinance


     January 17, 2006

     Jerry Thompson
     Johnny onthe Spot
     5292 South StateRoad 10
     Knox, IN 46534

     Dear Mr. Thompson,

     The City of Plymouth Wastewater Treatment Facility will be accepting residential septage generated from Marshall Co. for the calendar year 2006. A renewal notice will be issued at the beginning of next year. The material will be accepted under the following guidelines:

  • Residential septage and portable toilet waste only.
  • Contact with plant personnel must be made before delivery.
  • Discharge shall only be accepted Monday thru Friday 7:00 a.m. to 4:00 p.m.
  • Discharge shall not be made on City holidays or weekends.
  • The facility reserves the right to deny hauler privileges to discharge at any time.
  • Grease trap material is prohibited.
  • All septage must meet State, Federal and Local requirements.
  • Manifests must be completed on each load.
  • Fees shall be $.04 per gallon.
  • Discharging may discontinue if adverse affects on the treatment plant are observed.
  • Contact of the Treatment Facility is advised prior to delivery to assure acceptance due to the treatment plant running at full capacity.
     This is only an option and a service to the area and septage haulers. This by no means is a requirement.

     If you have any questions, contact me at (574)936-3017.

     S/Donnie Davidson, Superintendent
     City of Plymouth Wastewater Department

     Rick Gaul gave a brief report on storm water activity.

     City Attorney Simanski referred to a previously presented sanitary sewer easement that the city was seeking to obtain from Keith and Arline Felix. The easement would be for a tract of land along Oak Road to be used for a pump station for sanitary sewer improvements. Simanski said that Mr. Felix asked that the

325
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JANUARY 23, 2006

city pay for his attorney fees to review the easment agreement. Simanski asked the board's wishes on the Felix's $450 bill for legal services from Ken Lukenbill.

     Trustees Cook and Greenlee moved and seconded to approve the $450 legal bill for the permanent easement donation. The motion carried.

     Trustees Greenlee and Cook moved and seconded to allow the salaried payroll for January 1-15, 2006 and the claims for January 23, 2006 as entered in Claim Register #2006. The motion carried.
     
     Appointments to the Common Construction Wage Committee: The awarding agency must appoint two people to serve on the committee: one to represent taxpayers and another to represent industry. Mayor Cook made a motion to appoint Jim Marquardt to represent taxpayers and Don Wendel to represent industry, and to serve on the common construction wage committee on behalf of the city. Trustee Greenlee seconded the motion. Motion carried.

     There being no further business to discuss, Trustees Greenlee and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:52 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

326
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 13, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, February 13, 2006, immediately following theWater Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:17 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski,  Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present.

     Trustees Cook and Greenlee moved and seconded to approve the minutes of the last regular  meeting on January 23, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for January 2006:

Plant Operations:
1)   Total flow in gallons                        59,740,839
2)   Average daily flow in gallons           1,927,124
3)   Monthly average in BOD removal          98.6%
4)   Monthly average in TSS removal           96.1%
5)   Monthly average in Ammonia removal 99.4%
6)   Servicing all mobile equipment.
7)   Converting chemical room to U.V. room.
8)   Rebuilt #2 intermediate pump.

Meetings Attended
1/5/06           State Board of Accounts Inspection.
1/9/06           Sanitary Board Meeting
1/11/06         Six employees attended the January meeting held at Del Monte by the Northern Indiana Operators    
                       Association on activated sludge treatment.
1/23/06         Sanitary Board Meeting and public hearing on the Cites proposed CSO-LTCP Phase 2.

Collection System:
1) Cleaned 0 linear feet of sewer lines.
  • 0' during service calls
  • 0' during preventive maintenance
2) Televised 0 linear feet of sewer lines
3) Mechanically removed roots from zero linear feet of sewer lines.
4) Removed approximately 0 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 0 gallons of potable water during sewer cleaning.
6) Performed murine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the
     submitted CSO-LTCP.

     Director of Public Works Rick Gaul reviewed the following information with the board:

Date: February 13, 2006

Sanitary Board of Trustees
               Jack Greenlee
               Steve Benczik
               Supt. Donnie Davidson

From: Rick Gaul

Copy: Mayor Gary Cook
           Toni Hutchings
          Joseph Simanski
          Donald Wendel - Michiana Contracting
          Mike Strang - Strang & Associates

Re: Infrastructure Acceptance into Public Domain
       PW-06-004

Michiana Contracting Inc. wishes to dedicate the infrastructure from their Planned Unit Development Section 1 of Neidlinger Park to the City of Plymouth. The P.U.D. commonly referred to as Neidlinger Park Phase I, is located south of Baker Street and east of Columbus Drive. Please, find below a summary of the departmental documental for review by each board:

Background
On June 8, 1996, Mark Gidley was present at the regular session of the Common Council (a copy of page 321 of the minutes is attached) to request for streets and street lighting to be accepted. The request was granted. According to previous conversations with Mike Strang, Michiana Contracting's consulring engineer, Michiana Contracting was under the assumption that all of the infrastructure was accepted at this time, because it went before the Common Council.

327
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 13, 2006

Since there is confusion regarding what was accepted and what was not accepted. Mr. Strang was requested to provide "as-builts" and cost estimates for the infrastructure to be accepted into public domain. Because of the above confusion/miscommunication in this phase itemized costs were not required. However, on all future public domain acceptance requests (example Phase II) an itemization of cost will be required.

Hence, we are requesting the respective boards to confirm/accept the infrastructure for public domain acceptance. This should clear up any issues that may arise in the future regarding ownership of the infrastructure.

Sanitary Board of Trustees
Please find the attached:
1. Plymouth Wastewater Treatment Facility letter recommending acceptance of the storm and sanitary sewers;
    dated 01-30-2006.
2. Plymouth Wastewater Treatment Facility letter itemizing the infrastructure to be accepted into public domain;
    dated 1-30-2006
3. Michiana Contracting infrastructure dedication request letter, dated 01-30-2006.
4. Strang & Associates, Michael Strang letter dated 01-24-2006, identifying the costs for the infrastructure to be
    dedicated [sanitary sewer $73,456 & storm water $171,334].
5. Aerial photos highlighting the sanitary and the storm sewer infrastructure to be received into public domain.

Summary
The total value of the infrastructure in this request is $584,670 received into the public  domain.

Documentation from each department is included in the Board Member and Superintendent Packets. Documentation for all of the departments is included in the remaining packets.

Excerpt from the June 8, 1998 council meeting minutes:

"Mark Gidley was present regarding streets in the Neidlinger Park Addition. He asked that Wilson Street from Baker to Illinois Streets, Illinois Street from Wilson St. to Dora Lane, Wilson Circle, and Dora Lane from Baker Street to the intersection of Illinois Street be accepted by the City. He also asked that the street lights on Wilson Street and Illinois Street also be accepted. He said they had met with Street Commissioner Arvesen and he has reviewed the installatons of the roads and streetlights.

Arvesen said he finds the street and street lights to meet City specifications. He said the  street department is ready to take them over.

Councilmen Schuh and Manuwal moved and seconded to accept the streets and streetlights. Motion carried by unanimous vote of members present."


Plymouth Wastewater Treatment Facility
900 Oakhill Avenue
Plymouth IN 46563

January 30,2006

Sanitary Board of Trustees,

All of the necessary information has been provided to this department for the dedication of the Storm and Sanitary Sewers for the Neidlinger - Michiana Phase I project.

Installations have been certified by a registered State of Indiana Engineer and punch list items completed. Approval shall be subject to the developer completing the final adjustment of the structures, castings prior to the pavement application. City Standards will be required - 18" or less from the finish grade of the casing to the first step. In addition the developer will be responsible for the protection of all structures currently in place during construction and until completion and official dedication of Neidlinger-Michiana Section 1, Phase 2 has been accepted.

It is my recommendation that the Sanitary Board of Trustees accept the proposed dedication of the Sanitary Sewer System identified in Attachment A, and Storm Sewer System identified in Attachment B.

S/Donnie Davidson, Superintendent
City of Plymouth Wastewater Department


Plymouth Wastewater Treatment Facility
900 Oakhill Avenue
Plymouth, IN 46563

1-30-2006

Quantities of Installed Infrastructure in Neidlinger Park - Michiana Phase t, 1998 Construction

Sanitary Sewers
 8" PVC = 1,145 ft.
12" PVC = 1,310 ft

328
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 13, 2006

Service Wyes
6" = 26

Manholes
11

Inlets
12

Castings
23

Storm Sewers
8" PVC = 76 ff.
12" PVC = 313 ft.
18" PVC = 333 ft
24" RCP = 128 ft.
30" RCP = 769 ft.
36" RCP = 187 fi.


Michiana Contracting
PO Box 929
Plymouth, Indiana 46563

January 30, 2006

City of Plymouth
Water Works Board of Trustees
Sanitary Board of Trustees
Board of Public Works and Safety

RE: Neidlinger Park- Dedication of Infrastructure, Section 1, Phase 1 (Installed in 1998)

We would like to appear at your various Board meetings on February 13, 2006 concerning infrastructure completed at Neidlinger Park in 1998. Until recently we believed that all facets of the infrastructure had been dedicated to and accepted by the City of Plymouth through an appearance by Mark Gidley at the Common Council on June 8, 1998. However, discrepancies have arisen concerning the acceptance of completed infrastructure. Therefore, we would like to appear before the Boards at this time to tie up any loose ends that remain.

Specifically, we would like to appear before the Water Works Board of Trustees to have the water lines accepted. We would also like to appear before the Sanitary Board of Trustees for acceptance of the sanitary sewer system and the storm drainage system.

Since records show that the streets and street lighting have already been accepted, it should not be necessary to request aoceptance of these items.

Sincerely,
S/Donald Wendel,
President


Strang & Associates
703 Dickman Street
Plymouth, IN 46563

January 24, 2006

City Utility Engineer
City of Plymouth
124 North Michigan Street
Plymouth, IN 46563

RE: Neidlinger Subdivision, Section I, Phase I

Dear Rick,

I have produced a drawing for the waterlines placed in Section I of Neidlinger's Subdivision. In addition, listed below are the costs associated with the installation of the infrastructure  placed in Phase I.

Water                             $ 78,786.00
Sanitary Sewer                73,456.00
Lighting                             60,000.00
Streets                            201,094.00
Storm Sewer                 171,334.00

Donnie has given me drawings that show the installation of the Sanitary and storm sewers, they are attached with this letter and a spreadsheet showing the as-built elevations. If there are additional items that you require, please let me know.

Sincerely,
S/ Mike Strang

329
REULAR SESSION, SANITARY BOARD Of TRUSTEES, FEBRUARY 13, 2006

Picture on file at Clerk-Treasurer's office.

330
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 13, 2006

Picture on file at Clerk-Treasurer's office.

331
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 13, 2006

     Trustee Benczik asked Don Wendel if he realized that he would have to modify castings to be put in any future streets. Wendel said he does.
  
     Benczik moved and Greenlee seconded to accept both the sanitary and storm sewers for Neidlinger Park, Michiana Contracting, Phase I. The motion carried.

     City Attorney Simanksi referred to the discussion at the last meeting regarding the sanitary sewer easement along Oak Road from Mr. and Mrs. Felix. Simanski said that atthe last meeting, me board approved payment of $450 for legal services for the Felix's. Simanski said mat the city is in receipt of the permanent easement and asked the board to formally accept the easement, so that the Felix's can execute and submit the deed for recording.

State of Indiana      )
                                   )  SS:
County of Marshall )

SANITARY SEWER EASEMENT
CITY OF PLYMOUTH, INDIANA
(Permanent)

That in consideration of One Dollar ($1.00) and other good and valuable consideration paid to Keith G. and Arline C. Felix Revocable Living Trust hereinafter referred to as Grantor, by and on behalf of the City of Plymouth, Marshall County, Indiana, hereinafter referred to as Grantee, the receipt of which is hereby acknowledged, Grantor hereby warrants that Grantor has title to said real estate, and Grantor does hereby grant, bargain, sell, transfer, dedicate and convey enter the Grantee, its successors and assigns, an easement with the right to erect, construct, install and lay, and therefore use, operate, inspect, repair, maintain, replace and remove, sanitary sewer, and appurtenances thereto, all of which is a part of the Grantee's sanitary sewer system over, under, across, and through the land of the grantor situated in City of Plymouth, Marshall County, State of Indiana, together with the right of ingress and egress over the adjacent lands of the Grantor, his successors and assigns, for the purpose of this easement, and said easement being described as follows:

The Permanent Easements, if applicable, are described in the easement descriptions which are attached as Exhibit "A".

The Grantee covenants to maintain the easement in good repair so that no damage will result from its use to the adjacent land of the Grantor, his successors and assigns.

In acquiring said easements and rights-of-way, the right shall be reserved to the Grantors of the real estate to use and fully enjoy said easement and right-of-way for all purposes not  inconsistent with the necessary and convenient uses thereof by Grantee, its successors and assigns, for the purposes aforesaid; provided that no structure shall be erected or permitted on the easement and right-of-way. The rights reserved by the Grantor shall include, but shall not be limited to, the right to cross small sections of me easement and right-of-way with reads, utilities, drains and the tike in such fashion as not to disturb Grantee's facilities or the operation or maintenance thereof.

The grant and other provisions of this easement shall constitute a covenant running with the land for the benefit of Grantee, its successors and assigns.

The undersigned persons executing this easement on behalf of Grantor represent and certify that they have been authorized to execute and deliver this easement.

In witness whereof, the said Grantor has hereunto affixed its name, this 31 st day of January, 2006.

S/Keith G. Felix, Trustee                                S/Arline C. Felix, Trustee



Exhibit "A"
Keith G. and Adine C. Felix Revocable Living Trust
To
City of Plymouth, Indiana
Description
Permanent Sanitary Sewer Easement

A permanent Sanitary Sewer Lift Station Easement over, under and across a part of the land as described in the deed attached in Exhibit "B"; the deed is as recorded in the Marshall County Recorders Office, Marshall County, Indiana, as the property of Keith G. and Arline C. Felix Revocable Living Trust and being more particularly described as follows:

A part of the Southeast Quarter of Section 6, Township 33 North, Range 2 East in Center Township, Marshall County, Indiana, more particularly described as follows:

Commencing at the Northwest Corner of Lot #33 of Westgate Addition Continued to the City of Plymouth, in the Northeast Quarter of the Southeast Quarter of said Section 6; thence North 00 degrees 23 minutes West, 178.00 feet; thence North 31 degrees 46 minutes West, 101.40 feet; thence North 89 degrees 21 minutes West, 213.00 feet; thence North 00 degrees 23 minutes West, 412.12 feet; thence South 89 degrees 09 minutes East, 617.70 feet on an established line; thence South 00 degrees 25 minutes East; 396.40 feet; thence South 88 degrees 46 minutes East 492.40 feet to the West Line of Oak Road; thence South 00 degrees 00 minutes West along said West Line of Oak Road, 262.40 feet; thence South 90 degrees West 20 feet to the Point of Beginning: thence continuing South 90 degrees West, 30.00 feet; thence North 00 degrees 00 minutes East parallel to said West Line of Oak Road, 55.00 feet; thence North

332
REGULAR SESSION, SANITARY BOARD Of TRUSTEES, FEBRUARY 13, 2006

90 East, 30.00 feet; thence South 00 degrees 00 minutes West parallel to said West Line of Oak Road, 55.00 feet to the Point of Beginning, containing 1650 square feet more or less.

Subject to all legal easements, rights of way and restrictions of record.

* There was not an Exhibit "B" attached.

     Trustees Cook and Benczik moved and seconded to formally accept the agreement with Felix's.  The motion carried. Simanski asked that the members sign the document this evening.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for January 16-31, 2006 and the claims for February 13, 2006 as entered in Claim Register #2006. The motion carried.

     Ron Liechty and Brent Martin were present to ask for a 90-day extension to pay the wastewater tap for Fairfield Garden Court.

     Trustees Greenlee and Benczik moved and seconded to approve the request. The motion carried.
   
     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded  to adjourn the meeting. Motion carried. The meeting adjourned at 6:27 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

333
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, FEBRUARY 27, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday,  February 27, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:09 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on February 13, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson announced that tomorrow the common construction wage determination would be held for the Oak Road/Hillcrest Avenue Project Phase 2, at which time the wage would be set for the project. He asked for the board's approval to proceed with advertising the balance of the project after the common construction wage committee meeting.

     Trustees Benczik and Greenlee moved and seconded to accept the common construction wage determination. The motion carried.

     Davidson said that he has requested a complete set of utility plans for the jail project for review.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for February 1-15, 2006 and the claims for February 27, 2006 as entered in Claim Register #2006. The motion carried.

     Mayor Cook announced that Steve Eckard had requested to be on the agenda to request service. Eckard has purchased the Davidson property that is being considered for annexation under Ordinance #2006-1901. Cook said that the way the ordinances reads, they board doesn't have much latitude until after annexation is complete.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:13 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

334
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MARCH 13, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, March 13, 2006, immediately follaNing the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:20 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski,  Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on February 27, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent announced that the Oak Road/Hillcrest Avenue Project has been advertised and the deadline for receiving bids is 4:30 on April 10th.

     City Attorney Simanski reviewed the foIlowing letters with the board:

Date: March 13, 2006

To: Sanitary Board of Trustees
                      Jack Greenlee
                     Steve Benczik
                     Superintendent Donnie Davidson

From: Rick Gaul

Copy: Mayor Gary Cook
           Toni Hutchings
          Joseph Simanski
          Sherry Luckey

Re: Infrastructure Acceptance into Public Domain
       Pilgrim Lane (Lowe's)
       PW-05-030

The items on Pilgrim Lane have been completed and are ready for acceptance into the public domain. Please find below a summary of the departmental documentation for review by each board:

Please find attached Lowe's Itemized bid documents along with the following breakdowns.

Sanitary Board of Trustees

Sanitary Sewer
None to be accepted.

Storm Sewer
Please find attached:
1. Plymouth Wastewater Treatment Facility letter recommending acceptance; dated 3-10-2006.
2. An itemized current value of the infrastructure being dedicated [$108,948.25].
3. The site plans highlighting the infrastructure to be received into public domain.

S/ Rick Gaul
Director of Public Works


March 10, 2006

Sanitary Board of Trustees,

All necessary information has been provided to this department for the dedication of the Storm Sewers for the Pilgrim Lane Extension (Lowe's) Project.

Installations have been certified by a registered Engineer and punch list items completed. All pipe and apparatus have been inspected by the City of Plymouth personnel.

It is my recommendation that the Sanitary Board of Trustees accept the proposed dedication of the Sanitary Sewer System identified in Attachment A, and Storm Sewer System identified in Attachment B.

S/ Donnie Davidson, Superintendent
City of Plymouth Wastewater Department

335
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MARCH 13, 2006

Picture on file at Clerk-Treasurer's office.

336
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MARCH 13, 2006

Picture on file at Clerk-Treasurer's office.

337
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MARCH 13, 2006

     Trustee Benczik asked if all the storm sewers had been televised to determine that their integrity as still good.

     Davidson said that the main lines had been televised and they had visually inspected the structures. Davidson said that there were several punch list items, but the contractor had successfully completed them. All of the pipelines and structures passed inspected. Davidson said that there were several hundred feet of storm sewer that did not appear to be properly protected during construction and had a lot of sand. The inspections took place after they had been cleaned. Davidson said that there were two curb inlets that had settled and a couple of yard inlets that had not been properly packed around. Those items have been corrected.

     Trustees Benczik and Cook moved and seconded to accept the storm sewer as approved by  Superintendent Davidson and Board of Works Director Rick Gaul.

     Superintendent Davidson presented the following report for February 2006:

Plant Operations:
1) Total flow in gallons                       52,004,432
2) Average daily flow in gallons           1,857,301
3) Monthly average in BOD removal          99.2%
4) Monthly average in TSS removal           96.9%
5) Monthly average in Ammonia removal 99.4%
6) Completed the calibration of all meters connected to the Aquatrol system.
7) Completed employee hearing evaluations program on 2-1-2006 by Audiometrics.
8) Received general safety training from Gibson Insurance Co.
9) Installed new access hatch on sludge tanker.
10) Received training along with the Public Works Director on the new surveying total station.

Meetings Attended
2/13/06           Sanitary Board Meeting
2/14-2/16/06 Three employees attended the annual conference held in Nashville, TN on sewer maintenance
                        equipment.
2/27/06           Sanitary Board Meeting

Collection System:
1) Cleaned 4,122 linear feet of sewer lines.
  • 752' during service calls
  • 3,370' during preventive maintenance
2) Televised 4,544 linear feet of sewer lines
3) Mechanically removed roots from zero linear feet of sewer lines.
4) Removed approximately 2 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 14,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the
     submitted CSO-L TCP.
8) Located utility structures on the east side of town using our CPS locator.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for February 16-28. 2006 and the claims for March 13, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded  to adjourn the meeting. Motion carried. The meeting adjourned at 6:25 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

338
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MARCH 27, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, March 27, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:08 p.m.

     Mayor Gary Cook presided for Trustee Benczik. City Attorney Simanski, Superintendent Donnie  Davidson, Assistant Superintendent Larry Hatcher, Secretary Hutchings and Director of Public Works Rick Gaul were also present. Trustee Greenlee was absent.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular  meeting on March 13, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson announced that they would be beginning construction on several storm sewer repairs and point repairs associated with the city's combined sewer overflow long-term control plan.

     Davidson said that IDEM has confirmed that the ten-year one-hour storm will be the city's design standard. Davidson said that the city will have to install flow meters on the overflows to demonstrate that the ten-year one-hour storm standard is being met. He said that this is all to be completed within five years of the approval of the plan. The plan is to be finalized and submitted by the end of this week. Approval should occur within sixty days.

     Trustees Cook and Benczik moved and seconded to allow the salaried payroll for March 1-15, 2006 and the claims for March 27, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to  adjourn the meeting. Motion carried. The meeting adjourned at 6:13 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary President
Sanitary Board of Trustees

339
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 10,2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, April 10, 2006 immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:12 p.m.

     Mayor Gary Cook presided for Trustee Benczik. City Attorney Simanski, Superintendent Donnie  Davidson, Secretary Hutchings and Director of Public Works Rick Gaul were also present Trustee Greenlee was absent.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on March 27, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     A legal notice was advertised in the Pilot News on March 13, 2006 for sealed bids for the Wastewater Improvement Project at Oak Road and Hillcrest Avenue, Sanitary Sewer Extensions.

     City Attorney Simanski opened and read aloud the following sealed bids:

Beer & Slabaugh, Inc., 23965 US 6 East, Nappanee, IN, 46550               $134,820.50

Haskins, Inc., 2520 Oak Road, Plymouth, IN, 46563                                   $154,503.55

Oselka Construction, 10900 Kruger Rd., Union, MI, 49129                        $203,431.15

Rieth-Riley Construction, 25200 SR #23, South Bend, IN, 46614             $198,733.00

Thomas Excavating & Welding, 9750 West 16th Rd., Argos, IN, 46501   $258,758.25

     Trustees Cook and Benczik moved and seconded to take the bids under advisement so they could  be reviewed by Superintendent Davidson and/or the city attorney. The motion carried.

     Superintendent Davidson presented the following report for March 2006:

Plant Operations:
1) Total flow in gallons                         69,330,264
2) Average daily flow in gallons            2,236,460
3) Monthly average in BOD removal           98.9%
4) Monthly average in TSS removal            96.4%
5) Monthly average in Ammonia removal 99.1 %
6) Installed air releases (3) on all intermediate pumps to prevent cavitations.
7) Rebuilt aeration gas clean system (hydrogen chloride).
8) Start up the facility's ultra violet disinfection system.
9) Replaced the pressure and vacuum sensors on the primary anaerobic digester gas mixing system.

340
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 10, 2006

10) Ford F-550 chassis was delivered on 3-29-06, which was then sent to W.A. Jones Truck Bodies & Equipment
       for the installation of the dump bed.

Meetings Attended
3/7/06   Two men attended Vactor training school.
3/13/06 Sanitary Board Meeting
3/27/06 Sanitary Board Meeting
3/28/06 Eleven wastewater employees attended Trench Safety Seminar conducted by Jeff Lew of Purdue
               University

Collection System:
1) Cleaned 4,760 linear feet of sewer lines.
  • 0' during service calls
  • 4,760' during preventive maintenance
2) Televised 3,633 linear feet of sewer lines
3) Mechanically removed roots from zero linear feet of sewer lines.
4) Removed approximately 3 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 24,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the
     submitted CSO-L TCP.
8) Started layout designs for repairs and replacement of sewer lines and structures within the proposed street
     pavement projects for 2006.
9) Completed GPS locating off all sewer structures in the city.
10) Started inlet cleaning program as required by MS4.
11) Located all ends of pipes for storm sewers entering the streams or river as required by MS4 regulations.

     Trustees Benczik and Cook moved and seconded to allow the salaried payroll for March 16-31, 2006 and the claims for April 10, 2006 as entered in Claim Register #2006. The motion carried.

     Mayor Cook presented the following proposed agreement:

                                                                                                               March 31, 2006

Plymouth Sewer Board
City Hall
124 North Michigan Street
PO Box 492
Plymouth, IN 46563

Re: Agreement for Financial Management Reports

Dear Board Members:

You have requested that H.J. Umbaugh & Associates, Certified Public Accountants, LLP (the "Firm") provide to the Plymouth Municipal Water Utility (the "Client") those services more fully set forth in Exhibit A hereto (the "Services")

Fees and Costs.
Fees charged for work performed shall be as shown in Exhibit A.

Billing Procedures.
Normally, you will receive a monthly statement showing fees and costs incurred in the prior month. Occasionally, we may bill on a less frequent basis if the time involved in the prior month was minimal or if arrangements are made for the payment of fees from bond proceeds. The account balance is due and payable on receipt of the statement and we reserve the right to charge 1% interest per month for outstanding unpaid balances over thirty (30) days from the date of billing. Once our representation has been concluded or terminated, a final billing will be sent to you. If requested to provide an estimate of our fees for a given matter, we will endeavor in good faith to provide our best estimate, but unless there is a mutual agreement to a fixed fee, the actual fees incurred on any project may be less than or exceed the estimate. Any questions or errors in any fee statement should be brought to our attention in writing within sixty (60) days of the billing date.

Termination.
Both the Client and the Firm have the right to terminate the engagement at any time after reasonable advance written notice. On termination, all fees and charges incurred prior to termination shall be paid promptly.

Accountants' Opinion.
In performing our engagement, we will be relying on the accuracy and reliability of information provided by Client personnel. We will not audit, review, or examine the information. Please also note that our engagement cannot be relied on to disclose errors, fraud, or other illegal acts that may exist. However, we will inform you of any material errors and any evidence or information that comes to our attention during the performance of our procedures, that fraud may have occurred. In addition, we will report to you any evidence or information that comes to our attention during the performance of our procedures regarding illegal acts that may have occurred, unless they are clearly inconsequential. We have no responsibility to identify and communicate significant deficiencies or material weakness in your internal control as part of this engagement. The procedures we perform in our engagement will be heavily influenced by the representations that we receive from Client personnel. Accordingly, false representations could cause material errors to go undetected. The Client, therefore, agrees to indemnify and hold us harmless for any liability and all reasonable costs (including legal fees) that we may incur in

341
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 10,2006

connection with claims based upon our failure to detect material errors resulting from false representations made to us by any Client personnel and our failure to provide an acceptable level of service due to those false representations.

The responsibility for auditing the records of Client rests with the Indiana State Board of  Accounts and the work performed by the Firm shall not include an audit or review of the records or the expression of an opinion on financial data.

Client Responsibilities.
It is understood that the Accountants will serve in an advisory capacity with the Client. The Client is responsible for management decisions and functions, and for designating an individual with suitable skill, knowledge or experience to oversee the services we provide. The Client is responsible for evaluating the adequacy and results of the services performed and accepting responsibility for such services. The Client is responsible for establishing and maintaining internal controls, including monitoring ongoing activities.

Additional Services.
Exhibit A sets forth the scope of the Services to be provided by the Firm. From time-to-time, additional services may be requested by the Client beyond the scope of Exhibit A. The Firm may provide these additional services and be paid at the Firm's customary fees and costs for such services. In the alternative, the Firm and the Client may complete a revised and supplemented Exhibit A to set forth the additional services (including revised fees and costs, as needed) to be provided. In either event, the terms and conditions of this letter shall remain in effect.

If the foregoing accurately represents the basis upon which we may provide Services to the Client, we ask that you execute this letter, in the space provided below setting forth your agreement.  Execution of this letter can be performed in counterparts each of which will be deemed an original and all of which together will constitute the same document.

If you have any questions, please let us know.

Very truly yours,
H.J. Umbaugh & Associates
Certified Public Accountants, LLP
By: S/ John Julien, Partner

                                                                                             EXHIBIT A
                                                                             Services Provided and Fees

Scope of Services

ARTICLE 1: Interim Period Reports:

1. Provide summary of funds available for capital improvements.
2. Analyze utility fund balances for compliance with outstanding bond ordinances and other legal and local
    requirements.
     a. Prepare schedule of suggested fund transfers and explanations as necessary (for Client approval).
     b. Analyze fund balances for funds available for capital expenditures.
3. Prepare analysis of year-to-date revenues and expenditures in comparison with the utility's revenues and
    expenditures budget or prior year-to-date actual results.
     a. Identify unusual variations from the revenues and expenditures budget.
     b. Provide explanation of adjustments as necessary.
4. Analysis of the transactions for the period to determine appropriateness and consistency of transaction
    posting.
     a. Provide proposed adjusting transactions if necessary (for Client approval).
     b. Provide explanation of adjustments as necessary.
5. Prepare reports and be available to attend one meeting with the officials of the Client to discuss findings and
    recommendations.

ARTICLE II: Year End Reports

1. Analyze utility fund balances for compliance with outstanding bond ordinances and other legal and local
    requirements.
     a. Prepare schedule of suggested fund transfers and explanations as necessary.
     b. Analyze fund balances for funds available for capital expenditures.
2. Prepare analysis of year-to-date revenues and expenditures in comparison with the utility's revenues and
    expenditures budget (as necessary).
     a. Identify unusual variations from the revenues and expenditures budget (for Client approval).
     b. Provide explanation of adjustments as necessary.
3. Assist the utility to prepare an annual budget of estimated revenues and expenditures (as necessary).
4. Obtain information from Utility officials, the Client's consulting engineers and/or other sources necessary to
    assist the Client in the development of a capital budget.
5. Provide evaluation of current rates.
6. Prepare the financial statements (without audit or review) for each utility.
7. Provide summary of capital asset activity for the year.
8. Provide summary of large users and usage Of available).
9. Analysis of the transactions for the period to determine appropriateness and consistency of transaction
    posting.
     a. Provide proposed adjusting transactions if necessary (for Client approval).
     b. Provide explanation of adjustments as necessary.
10. Prepare reports and be available to attend one meeting with the officials of the Client to discuss findings and
    recommendations.

342
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 10, 2006

Fees.
The Accountant's charges for services and expenses in connection with the services to be rendered as set forth in Articles 1 and 2 above shall be based on the following table for reports issued in 2006. For reports issued thereafter, the annual fee will be adjusted by an amount not to exceed three percent (3%) per year.

                    Interim Period Reports:
                                  April Report        $3,250
                                 August Report       3,250

                    Year-End Report               3,250
                              Total Annual Fee  $9,750

     Superintendent Davidson said that it's a good investment given the number of capital improvement project that the department has planned in the next three to five years.

     Trustees Cook and Benczik moved and seconded to accept the agreement as proposed by  Umbaugh. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to  adjourn the meeting. Motion carried. The meeting adjourned at 6:23 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

343
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 24, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, April 24, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:18 p.m.

     Mayor Gary Cook presided for Trustee Benczik. City Attorney Simanski, Superintendent Donnie  Davidson and Director of Public Works Rick Gaul were also present Deputy Clerk-Treasurer Xaver was present in the absence of Secretary Hutchings. Trustee Greenlee was absent.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on April 10, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson reviewed the following recommendation with the board:

Commonwealth Engineers, Inc.
7256 Company Drive
Indianapolis IN 46237

April 20, 2006

Plymouth Sanitary Board of Trustees
City Hall
124 North Michigan Street
Plymouth, Indiana 46563

Re: Engineer's Recommendation

Wastewater Improvements Project
Oak Road Sanitary Sewer Extensions

Gentlemen:

We have reviewed the five (5) bids submitted for the Oak Road Sewer Extension Project. We have found Beer & Slabaugh, Inc. of Nappanee, Indiana to have submitted the lowest responsive, responsible bid in the amount of $134,820.50. We have attached with this letter certified bid tabulations for the project.

It is our recommendation, pending the review by the City's Attorney, that the City make award to Beer & Slabaugh, Inc.

If you have any questions, please contact us.

Sincerely,
Commonwealth Engineers, Inc.
S/Mark M. Sullivan, P.E.
Project Manager

     Davidson said that the variations in the bids are primarily due to overhead and the current work load of the bidders.

     Trustees Benczik and Cook moved and seconded to accept Commonwealth's recommendation and  to award the bid to Beer & Slabaugh, Inc. in the amount of $134,820.50. The motion carried.

     Davidson reported that the temporary pavement that was put down on Hoham Drive early last winter for the sewer extension project by Western Avenue is due to be replaced by the contractor next week. Davidson said that due to weather conditions at the time of installation, the pavement intended to be temporary and was expected to fail and the city kept enough retained to make sure the resurfacing would be done. Davidson explained that when the asphalt was installed at the correct temperatures, but the next day the temperatures dropped below what was actually acceptable. Due to the time of year, the weather and the closing of the asphalt plants the next day, the contractor went ahead and put surface down with the understanding that it would be temporary and it would have to be milled and resurfaced in the spring.

     Director of Public Works Rick Gaul reviewed his first quarter report with the board.

     Trustees Cook and Benczik moved and seconded to allow the salaried payroll for April 1-15, 2006 and the
claims for April 24, 2006 as entered in Claim Register #2006. The motion carried.

344
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, APRIL 24,2006

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to  adjourn the meeting. Motion carried. The meeting adjourned at 6:24 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

345
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MAY 8,2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, May 8, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:30 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on April 24, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for April 2006:

Plant Operations:
1) Total flow in gallons                        59,765,352
2) Average daily flow in gallons           1,992,178
3) Monthly average in BOD removal          93.3%
4) Monthly average in TSS removal           97.2%
5) Monthly average in Ammonia removal 99.2%
6) Replaced bracing on distributor arms on both bio-roughing towers.
7) Worked with the Engineering Dept. on the operation of the new "Total Station".
8) Land applied 1,860,800 gallons of bio-solids to local farm fields.
9) Cleaned all boiler tubes. Replaced 2 tubes, which were plugged with scale and sludge. Boiler uses methane gas which is a byproduct of our operation.
10) Ford F-550 chassis and dump bed were delivered on 4-13-06 from W.A. Jones Truck Bodies & Equipment
11) Rebuilt chlorine feed system for the plant's return sludge.
12) Replaced all water valves (4) in polymer feed room.
13) Terry Scott completed Class 2 Municipal Wastewater IDEM exam.

Meetings Attended
4/10/06 Sanitary Board Meeting
4/24/06 Sanitary Board Meeting
4/25/06 Drainage study progress meeting with Roger Klottlowski, Larry Fisher, and Rick Gaul on the Rightly Ditch.

Collection System:
1) Cleaned 750 linear feet of sewer lines.
  • 750' during service calls
  • 0' during preventive maintenance
2) Televised 367 linear feet of sewer lines
3) Mechanically removed roots from 202 linear feet of sewer lines.
4) Removed approximately 1 ton of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 17,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP.
8) Repaired storm sewer in Tall Oaks.
9) Completed 3 point repairs (JHR) and (1) Flora St. and Harrison St.
10) Installed 2 new inlets on E. LaPorte St.
11) Continued inlet cleaning program as required by MS4.
12) Installing stormwater markers on all public storm sewer inlets (approx. 185).
13) Tapped 30" RCP with 12" PVC storm sewer on Wilson St.

     Davidson reported that the department has started installing stormwater markers on all public  storm inlets that drain to the river.

     Davidson reported on the Oak Road project south of Jefferson Street. Commonwealth Engineers have provided Beer & Slabaugh the notice of award on the contract; the notice to proceed should be  given by the 14th and work should begin by May 28th.

     Davidson updated the board on Hoham Drive. There have been delays because of the weather and the local asphalt plant has not yet opened. The contractor is looking at other sources of asphalt material.

     Trustees Cook and Benczik moved and seconded to allow the salaried payroll for April 16-30, 2006  and the claims for May 8, 2006 as entered in Claim Register #2006. The motion carried.

     Ron Liechty, chairman of the board of directors of Fairfield Garden Court. Liechty said that on  December 12, 2005, the board granted an extension to them for the sanitary sewer tap fee due to their difficulty in obtaining not-for-profit status through the IRS. Liechty asked for an extension of that deferral.

346
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MAY 8,2006

     Trustees Greenlee and Benczik moved and seconded to approve a 180 day extension. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded  to adjourn the meeting. Motion carried. The meeting adjourned at 6:35 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

347
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, MAY 22,2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, May 22, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:18 p.m.

     Mayor Gary Cook presided for Trustee Greenlee. City Attorney Simanski, Superintendent Donnie  Davidson, Assistant Superintendent Larry Hatcher, Director of Public Works Rick Gaul and Secretary Hutchings were also present. Trustee Benczik was absent.

     Trustees Greenlee and Cook moved and seconded to approve the minutes of the last regular meeting on May 8, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Trustees Cook and Greenlee moved and seconded to allow the salaried payroll for May 1-15,  2006 and the claims for May 22, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Cook and Greenlee moved and seconded to  adjourn the meeting. Motion carried. The meeting adjourned at 6:19 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

348
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JUNE 12, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, June 12, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:24 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on May 22, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for May 2006:

Plant Operations:
1) Total flow in gallons                        71,290,928
2) Average daily flow in gallons           2,299,707
3) Monthly average in BOD removal          99.1%
4) Monthly average in TSS removal           97.2 %
5) Monthly average in Ammonia removal 99.1 %
6) Repaired concrete finish on all plant process tanks.
7) Repaired the roof flashing on the secondary control building.
8) Relocated automatic rain gauge to the north end of the city for CSO-L TCP requirements.
9) Reconditioning #2 raw sewage pump.
10) Fabricating air release valves for raw sewage pumps.

Meetings Attended
5/8/06 Redevelopment Meeting - Rightly Ditch
5/8/06 Sanitary Board Meeting
5/11/06 Traffic Zone Safety Training - Gibson Ins.
5/22/06 Sanitary Board Meeting

Collection System:
1) Cleaned 7,665 linear feet of sewer lines.
  • 0' during service calls
  • 7,665' during preventive maintenance
2) Televised 0 linear feet of sewer lines
3) Mechanically removed roots from 7,665 linear feet of sewer lines.
4) Removed approximately 2 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 15,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP.
8) Continue installing stormwater markers on inlets.
9) Installed new inlet at 500 W. Harrison St.
10) Replaced existing inlets at: Gilmore St. - Pierce St. and Dickson St. - Washington St. and Plum St - Plum St. and Adams St.
11) Repaired generator on sewer camera unit.
12) Preventive maintenance on the sewer system problems sewers.

     Superintendent Davidson reported that they have started the layout on the Oak Road / Hillcrest Avenue Project and hope to be placing the sewer line within the next two weeks. Davidson said that the contractor has a 45-day time limit for the substantial completion of the lift station and the sanitary sewer lines.

     Davidson said that the Hoham Road surface is to be remilled and resurfaced. He hopes that will be done in the next couple of weeks, but are still struggling with the availability of asphalt.

     City Attorney Simanski presented a request from the county to waive the performance bond in regard to the utility infrastructure for the new jail that is being built on Pine Road and Jim Neu Drive.

ACKNOWLEDGEMENT THAT UTILITY INFRASTRUCTURE FOR THE
MARSHALL COUNTY CORRECTIONAL FACILITY WILL COMPLY
WITH CITY OF PLYMOUTH SPECIFICATIONS AND WAIVER OF BOND

This agreement made and entered into this ___ day of ________, 2006, by and between Marshall County ("County") and the City of Plymouth ("City"), agree as follows:

1.     That County will construct utility infrastructure, including waterlines, sewer lines, and other utilities in compliance with City specifications for such utilities for the Marshall County Correctional Facility to be located at 1400 Pine Road, Plymouth, Indiana. In accordance with Indiana Code 36-1-12-14(e), the County has required contractors performing said utility infrastructure construction to furnish the County with a performance bond equal to the  

349
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JUNE 12, 2006

contract price. In the event a contractor fails to perform the construction of the utility infrastructure in accordance with the specifications of the City, the County will seek to enforce compliance and, if necessary, pursue the appropriate action against the surety on the performance bond. The County agrees to include the City in said action or assign the performance bond to the City if necessary.

2.     The City waives the requirement of the County to provide a separate performance bond for the construction of utility infrastructure for the Marshall County Correctional Facility Project at the intersection of Jim Neu Drive and Pine Road.

3.     County agrees to keep City fully advised as to the status of said construction and to seek City's approval that the utility contractors are in compliance with City specifications.

Dated this ____ day of __________,2006.

     Trustee Benczik asked if there is a provision or allowance for the sewer department to review the site and make sure they are getting proper connection and proper compaction, and if there's a deflection test. Benczik said that "conforming to the specs" to him means allowing a wastewater treatment plant employee to inspect the work before it's covered up.

     Simanski referred to #3 of the proposed agreement.

     Trustee Benczik moved that the Sanitary Board of Trustees make a recommendation to the Common Council to enter into the agreement, as amended, with the county on the waiver of the bond.

     Trustee Greenlee seconded the motion. Motion carried.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for May  6-31, 2006 and the claims for June 12, 2006 as entered in Claim Register #2006. The motion carried.

     Don Dimmitt, owner of 113-115 S. Michigan Street, addressed the board regarding a bill that he would like to dispute. Dimmitt said that any water that was used must have run on the ground, so he doesn't feel that he should have to pay the sewer charge.

     Benczik referred to the explanation that Water Superintendent Yeazel gave at the Water Works Board of Trustees meeting referring to a corresponding wastewater bill for water used.
   
     Trustees Benczik and Cook moved and seconded to reject the request. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to  adjourn the meeting. Motion carried. The meeting adjourned at 6:32 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, Presiding Officer
Sanitary Board of Trustees

350
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JUNE 26,2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, June 26, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:13 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Assistant Superintendent Larry Hatcher, Director of Public Works Rick Gaul and Secretary Hutchings were also present. Superintendent Donnie Davidson was absent

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on June 12, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Assistant Superintendent Hatcher reported on the Oak Road Project. He reported that they have about 300' of gravity line to install then they will move to the lift station and tie in the force main. They are hoping to have the gravity line finished tomorrow.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for June 1-15, 2006 and the claims for June 26, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded  to adjourn the meeting. Motion carried. The meeting adjourned at 6:14 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

351
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JULY 10,2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, July 10, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:21 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on June 26, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for June 2006:

Plant Operations:
1) Total flow in gallons                        56,643,164
2) Average daily flow in gallons           1,988,105
3) Monthly average in BOD removal          99.4%
4) Monthly average in TSS removal           97.7 %
5) Monthly average in Ammonia removal 99.0 %

Meetings Attended
6/12/06 Sanitary Board Meeting
6/26/06 Sanitary Board Meeting
6/28/06 Three men attended NIOA meeting in Elkhart on GIS applications for industrial pretreatment.

Collection System:
1) Cleaned 8,139 linear feet of sewer lines.
  • 3,838' during service calls
  • 4,856' during preventive maintenance
2) Televised 3,283 linear feet of sewer lines
3) Mechanically removed roots from 0 linear feet of sewer lines.
4) Removed approximately 6 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 68,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP.
8) Continue installing stormwater markers on inlets.
9) Completed final inspection on Eastwood Estates - Section 3.
10) Installed new inlets:
        1 - 500 Rose St.
        3 - Berkley St. between Liberty St. and Randolph St.
11) Replaced inlets with new precast structures
        3 - Monroe St. and Walnut St.
        3 - Randolph St. and Berkley St.
12) Installed 1 new 48" sanitary manhole on Berkley St. between Liberty St. and Randolph St.
13) Replaced 2 brick sanitary manholes with precast concrete manholes in alley between Poplar St. and Oakhill Ave.
14) Completed 2 point repairs on the sanitary sewer on Randolph St. in front of the high school.

     Superintendent Davidson reported on the sanitary sewer extension project on Oak Road by Hillcrest Avenue. Davidson said that the gravity sewer is completed and installed up to Pratt retail store; the wet well and valve vault have been installed, but they are still waiting on pumps; they have about 150' of force main on Hillcrest left and to test the project; they have started reinstalling culverts and landscaping.

     Davidson reported that his department has completed the construction project in the area of Randolph and Berkley Streets, although there is still surface work to complete.

     Superintendent Davidson reported that his department has been replacing storm sewer inlets and storm sewers. Davidson said that they have also been separating some sewers in several areas around town in accordance with the combined sewer overflow long term control plan.

     Davidson said that Todd Trinkle from IDEM has contacted him regarding the submitted CSO-L TCP. Trinkle said that IDEM is in the process of reviewing the plan again and intends to have a comment letter in two weeks.

     Director of Public Works said that he is working on the IDEM Municipal Separate Storm Sewer  System (MS4) yearly report that is due the end of July.

352
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JULY 10,2006

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for June 16-30, 2006 and the claims for July 10,2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded  to adjourn the meeting. Motion carried. The meeting adjourned at 6:24 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

353
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, JULY 24, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, July 24, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:33 p.m.

     Mayor Gary Cook presided for Trustee Greenlee. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present Trustee Benczik was absent.

     Trustees Greenlee and Cook moved and seconded to approve the minutes of the last regular meeting on July 10, 2006, and to dispense with reading them since they have been reviewed and  found to be correct, motion carried.

     Superintendent Davidson said that the sanitary sevver extension project on Oak Road by Hillcrest Avenue is progressing, but they are waiting on control panel and pumps for the pump station. Davidson said that they are waiting for asphalt for some projects, since they don't have the convenience of getting asphalt on King Road as they need it. Davidson said that for that reason they try to coordinate several asphalt jobs at once.

     Davidson said that today he received the review from IDEM for the Combined Sewer Overflow Long Term Control Plan. IDEM has asked the city to remodel the system using a different rainfall frequency. IDEM believes that Plymouth falls into a different region that what the system was modeled with. This could require that the system be designed for an additional amount of rainfall, which could result in additional storage requiremen1s and minor corrections to phase two of the plan. Davidson said that it appears that IDEM has agreed to give the city five years to complete phases one and two. Davidson said the combined cost of the two phases is $6,114,000. Davidson estimated they have reduced the cost of phase one by about half by completing a lot of the work in-house and within the budget. Davidson said that he will be submitting all of the in-house work to IDEM to verify the expenses that they have incurred. He will resubmit the data that IDEM requested, hopefully within forty-five days.

     Director of Public Works Rick Gaul announced that he has completed the 2005 Municipal  Separate Storm Sewer System (MS4) report.

     City Attorney Simanski read Resolution #2006-267, A Resolution of the Sanitary Board of Trustees Recommending Approval of the 2007 Holiday Ordinance #2006-1910) and the 2007 Salary Ordinance (#2006-1911).

     Trustees Cook and Greenlee moved and seconded to adopt Resolution #2006-267, A Resolution of the Sanitary Board of Trustees Recommending Approval of the 2007 Holiday Ordinance #2006-1910) and the 2007 Salary Ordinance (#2006-1911). The motion carried.

     Trustees Greenlee and Cook moved and seconded to allow the salaried payroll for July 1-15, 2006 and the claims for July 24, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Greenlee and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:39 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

354
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, AUGUST 14, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, August 14, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:36 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on July 24, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for July 2006:

Plant Operations:
1) Total flow in gallons                        65,538,428
2) Average daily flow in gallons           2,114,142
3) Monthly average in BOD removal          98.9%
4) Monthly average in TSS removal           97.6 %
5) Monthly average in Ammonia removal 99.0 %
6) Received comment letter from IDEM on the city's CSO-LTCP.
7) Repaired fuel monitoring system that was damaged during thunderstomr on 7-14.
8) Power outage for 9 hours on 7-14 due to storms.

Meetings Attended
7/10/06 Sanitary Board Meeting
7/12/06 Two operators attended NIOA meeting held at Tippecanoe State Park on Low Pressure Sewer Systems
7/14/06 Greenways preconstruction meeting
7/24/06 Sanitary Board Meeting

Collection System:
1) Cleaned 1,495 linear feet of sewer lines.
  • 0' during service calls
  • 1,495' during preventive maintenance
2) Televised 687 linear feet of sewer lines
3) Mechanically removed roots from 0 linear feet of sewer lines.
4) Removed approximately 15 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 104,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP. The trunk line on Polk St. is currently being cleaned along with both river siphons at the Magnetic Park and Cleveland St.
8) Continue installing stormwater markers on inlets.
9) Replaced inlets:
        4 - at the intersection of Nursery St. and Thayer St.
        2 - at the intersection of S. Michigan St. and Dickson St.
10) Repaired forced main in the 2400 block of N. Michigan St.

     Superintendent Davidson said that the pumping station, gravity sewer, forced main, pumps and control panel on the sanitary sewer extension project on Oak Road by Hillcrest Avenue have been installed. NIPSCO is in receipt of the city's agreement to supply electric service to the pump station. NIPSCO said that service would be provided within two or three weeks. Barring any problems, he foresees the houses being connected to the new system within one month.

     Davidson said that he has implemented a notification program for the wastewater treatment department on road closures, which includes local media, emergency services and other departments which may be involved. He said that sometimes his department does not receive sufficient notice from its suppliers and asked for the public's patience.

     Director of Public Works Rick Gaul presented a request from Contemporary Construction asking that the infrastructure in Eastwood Estates, Third Section be accepted into the public domain. Gaul reviewed information and said that the infrastructure and detention pond is built to standards. The value placed on the sanitary storm sewer is $109,581.00 and the value on the storm drainage infrastructure is $78,744.00.

355
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, AUGUST 14, 2006

     Trustees Benczik and Greenlee moved and seconded to accept the infrastructure, contingent upon acceptance by the other boards. The motion carried.

     Trustees Greenlee and Cook moved and seconded to allow the salaried payroll for July 16-31, 2006 and the claims for August 14, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:42 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

356
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, AUGUST 28, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, August 28, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:14 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on August 14, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson reported that the sewer project on Pennsylvania Avenue that was scheduled to start today has been delayed due to the rain. His intent is to do as much construction as possible through Thursday, then backfill the area and re-open the street to traffic for the weekend.

     City Attorney Simanski opened the floor for discussion on the interlocal agreement between Marshall County and the City of Plymouth in regards to the construction of the jail/correctional facility by the county at Pine Road and Jim Neu Drive.

     Wastewater Treatment Plant Superintendent Donnie Davidson reviewed the following letter:

     8-28-06

Based upon the concept that sewer connection fees are the actual purchase of capacity within the Collection System & Treatment Plant, the proposal appears to address the capacity that would be lost due to the new facility. This does appear to be a fair and reasonable solution to this issue.

This is a much better solution than the County's original request which essentially was "give us $380,000." This meets both County and City concerns:


County - To reduce original fee by $280,000.

City - The spirit of the rate ordinance is met by the actual lost capacity being paid for the same as previous connections.

I do believe the agreement does need to be adjusted in the best interest of the City of Plymouth and the Wastewater Utility.

By the completion of the jail project City and County officials may have changed. Along with change come different ideas on how the property should be used. With over a quarter of a million dollars in the balance, I feel the agreement should be more specific and allow little or no wiggle room from what the City assumed we were receiving.

Please find below a list of items that need to be addressed:

1.  The rate ordinance must be amended to reflect the agreement and to address future requests, this
     sets a precedent and there will be future requests.

     The new sanitary sewer system and lift station shall be extended as approved, to City Standards and
     dedicated to the City of Plymouth upon completion.

2.  The language in the proposed agreement is very loose, such as:
     Recitals C,
     "it is the intention".
     County Intends to construct a parking lot".
     County agrees that it's present intention".
     "However, in the event the county does not demolish the existing jail..."
     "At the present time, all projects are estimated to be completed by the end of 2008".

3.  The language should state the current jail shall be demolished and it shall be demolished within 6
      months of occupying the new facility (or whatever would be reasonable time frame).

     The existing connection shall be disconnected at the county's expense and the mainline repaired to City
     Standards within 30 days after occupying the new facility.

4.  Any change of use other than demolition of the current jail would require the proposed plan to be
     presented to the City of Plymouth Sanitary Board and Common Council for review and approval, which
     would include wastewater discharge volumes and the appropriate tap fees paid.

5.  Requirements follow the property's deed, in the event there is a sale of the property.

6.  The agreement should not be tied to any other City - County projects. Reasons are City rate payer
     dollars vs. tax dollars.

357
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, AUGUST 28, 2006

7.  Using the new jail projected usage of 29,760 gpd less current facility's usage of 21,328 gpd the
     difference equals 8,432 gpd. Using the City's current connection fee formula:
        8,432 X 4/411 X $1,314 = $107,831.12

     The actual fee should be $107,831.12

8.  I assume this agreement does not include water tap fees.

     If you have questions, contact me at (574)936-3017.

     S/ Donnie Davidson, Superintendent
     City of Plymouth Wastewater Department

     Davidson said, "I did have some issues with some of the language within the agreement. I felt that it did need to be specified with a very clear timetable on when certain milestones will be met, such as the disconnection of the existing sewer tap to the existing facility. And some other items which Joe has also reviewed and I've been working with him to adjust the agreement. The difference in the county proposal $100,000 fee, I do feel that it's important that we use the same formula which all other customers have used up to this point. What we have arrived at is the exact difference between what the current jail is using and what the projected flows are going to be for the new facility. Back a couple of months ago, Tom and I sat down and evaluated the current usage of the jail and how we arrived at those figures, is we used the last twelve months worth of usage to determine those gallons per day usage. At the last meeting, I was very hesitant using the 21,000 gallon figure, which everybody seemed to pick up on and use, but the actual consumption was 21,328 gallons, so although I used a round number, it does make a considerable difference when we are talking this type of fee. So that's how there is a difference in the proposed connection fee compared to what I had come up with."

     City Attorney Simanski reviewed items going into the proposed agreement that he's going to do.

     Building Commissioner Dennis Emmons said that he is holding a check from the county in the amount of $240 for the building permit fee. Emmons said that the fees as of September 1st are  $1,860.

     Trustee Benczik questioned whether the Sanitary Board of Trustees should approve the  agreement Benczik said, 'We went through, many years ago, a rate study, to set the tap fees. The tap fees, as everybody has heard, are set up so that the future capacity of the treatment plant is going to be there for future use. If you have a tap fee for an industrial user and for the jail and for users of water and water that goes into the sewer, that's there to be used for capacity in the treatment plant. We have a superintendent here who has made extraordinary efforts to make sure that the extra storm water infiltration is taken out of the system, so that gives us extra capacity. We've hired consultants like Commonwealth Engineering, who have been working with the system for many years, they know the system, they've worked with Donnie; they've worked with IDEM and our rate consultant, H.J. Umbaugh to come up with these charges and tap fees, and it was made into an ordinance, which to me is a law. So this wasn't a thing that was thought up lightly. This was done through a lot of study, many consultants worked on it. We have Donnie and his staff who have worked on it. So those charges for tap fees are the best thing that we've got. These rates were adopted. I think when you're trying to compare the actual sewer usage from the past jail to the proposed jail, I think that is more of a user type thing, that's how much sewage is actually going to be put into the system. So if you want to compare that to tap fees, to me you are comparing apples and oranges. The user is paying so much per month for the amount of sewage that's going to be used - that's something that's charged each month, that's what everybody pays in the city - based on actual usage. When you are talking about rate charges, that's a totally different system. I don't think you're looking at the same thing. I think that the tap fee should be as is. I know that there are other issues that are involved with the Rightley Ditch and other joint projects that are going on. But from my standpoint on the sewer board, I

358
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, AUGUST 28, 2006

represent the City of Plymouth, and I think that it is not in the best interest of the City of Plymouth and the taxpayers of Plymouth to go ahead and waive $180,000 or $280,000 worth of tap fees. That's the amount of water that they use; that's the rate that was set up; I think they should pay it. My recommendation would be not to accept the amount that is in the agreement."

     Audience Member Wilson Gerrard agreed, stating that the county should have to follow the same rate structures as citizens.

     City Attorney Simanski said that in recognition of the fact that we are dealing with an exceptional situation because the county will take a structure down that is using quite a bit of our sewer capacity at this point. He said they will be removing roughly 21,000 gallons of usage from going into our system, and replacing it with a facility that is estimated to use 29,000 gallons of usage. The existing jail structure will be removed and we are asking them to remove the sewer and water taps from that location so that it will not have the capability of being sold and used and using up any capacity. Simanski said that the net affect of taking one facility offline and putting the new facility online is 8,000 gallons per day.

     Superintendent Davidson said, ''The county is extending service from the existing location in front of the Witt Corporation, at our last gravity manhole, and they will run a forced main from that manhole under the ditch back to the access drive to the jail from Jim Neu Drive; install a lift station; they will also install a gravity line to the south towards the jail all to city standards. At this point, the city only has a desire of accepting 400' of that so that we can also serve a property located adjacent to the jail property between the ditch and the new jail property. The lift station was oversized to accommodate all of the outparcels along Jim Neu Drive. I have explained to the county commissioners that at the time of extension from that lift station to the west, that will be the same as subdividing a parcel and they will be required to extend services to the west to serve those outlots at their expense. Right now the oversizing does exist and the intent is for the county to install everything to city standards and dedicate the system to the city. They estimate the infrastructure improvement to be worth about $180,000."

     After verifying that the taps at the existing jail site would be eliminated, Trustee Benczik said that he understands the rational of the $107,831.12 sewer tap fee.

     Trustee Greenlee make a motion to accept the new proposal and recommend that the council also accept the interlocal agreement counterproposal from the City of Plymouth. Trustee Benczik seconded the motion. The motion carried.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for August 1-15, 2006 and the claims for August 28, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:43 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

359
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, SEPTEMBER 11, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, September 11, 2006, immediately following the Water Works Board of Trustees meeting in the  Council Chambers of the City Building, 124 N.Michigan Street, PIymouth, IN The meeting was called to order at 6:14 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on August 28, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

    Superintendent Davidson presented the following report for August 2006:

Plant Operations:
1) Total flow in gallons                        66,352,940
2) Average daily flow in gallons           2,140,417
3) Monthly average in BOD removal          98.9%
4) Monthly average in TSS removal           96.2%
5) Monthly average in Ammonia removal 99.1%
6) Clyde Avery, Marshall Co. Emergency Management Director provided NIMS training on 8-2. All employees have completed the required testing.
7) Repaired walls on both bio-roughing towers.
8) Cleaned aeration system using hydrochloric gas.
9) Flow meters calibrated 8-8-2006.
10) Lightning damaged the lift station monitoring system (SCADATA) on 8-9-2006.
11) Provided a plant tour for approximately 18 Plymouth building trades students on 8-30.

Meetings Attended
8/7/06   Budget Workshop
8/9/06   Two men attended NIOA meeting at Potato Creed on 'Water is Life".
8/11/06 Sanitary Board Meeting
8/15/06 Stormwater Utility
8/21/06 Marshall County Jail tap fees
8/22/06 Three men attended meeting on the changes in diesel fuel, presented by Fulton-Marshall LP
8/28/06 Sanitary Board Meeting

Collection System:
1) Cleaned 4,486 linear feet of sewer lines.
  • 0' during service calls
  • 4,486' during preventive maintenance
2) Televised 1,156 linear feet of sewer lines
3) Mechanically removed roots from 2,286 linear feet of sewer lines.
4) Removed approximately 0 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 14,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP. The trunk line on Polk St. is currently being cleaned along with both river siphons at the Magnetic Park and Cleveland St.
8) Completed installing stormwater markers on inlets.
9) Replaced inlets:
     2 - at the intersection of North St and Plum St.
     1 - at the intersection of Pennsylvania Ave. and Liberty St.
     1 - at the intersection of Michigan St. and Charles St.
     1 - at the intersection of Water St. and Washington St.
     1 - at 308 E. Garro St.
10) Installed forced main at the Ferndale St. pump station.
11) Selge Construction connected force main to City sewer from the Pretty Lake Conservancy District.
12) Started replacing sanitary manholes and main line in the 700 block of Pennsylvania Ave.
13) Replaced existing manhole and 100' of 8" sanitary sewer at Liberty St. and LaPorte St.
14) Disconnected resident from storm sewer and reconnected to the correct sanitary sewer in the 100 block of N. 3rd St.

     Superintendent Davidson reported that the sanitary sewer repair project on Pennsylvania Avenue has been delayed for a couple of days due to rain, but he anticipates completing the project this week.

     Davidson reported that Selge Construction, the contractor for the Pretty Lake Conservancy District, has made connection to the city's mainline sewer at Tall Oaks Subdivision and plan to connect the homes in the next couple of weeks. Davidson said that at that time his department would begin receiving wastewater from the conservancy district

360
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, SEPTEMBER 11, 2006

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for August 16-31, 2006 and the claims for September 11, 2006 as entered in Claim Register #2006. The motion carried.

     John Julien, Umbaugh and Associates, presented written information to the board regarding the proposed storm water utility, which will fund the new state and federal mandates regarding storm water. Julien said that the council would be considering ordinances regarding the storm water utility and rates.

     Julien said that the department heads do an excellent job of staying ahead of the curve, and doing it in a very cost-effective way that meets the requirements.

     Davidson said that the storm water utility will be under the jurisdiction of the Sanitary Board of Trustees, but the department will be managed by Rick Gaul. Davidson stressed that presently they are only addressing water quality issues, not water quantity issues.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:50 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

361
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, SEPTEMBER 25. 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, September 25, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:19 p.m.

     Mayor Gary Cook presided for Trustee Greenlee.. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher and Director of Public Works Rick Gaul were also present. Deputy Clerk-Treasurer Xaver was present in the absence of Secretary Hutchings. Trustee Benczik was absent.

     Trustees Cook and Greenlee moved and seconded to approve the minutes of the last regular meeting on September 11, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson reported that the sanitary sewer repair project on Pennsylvania Avenue has been delayed due to the concrete contractor reinstalling curbs. He estimated the contractors will be completing the project in about a week.

     Davidson reported on the Oak Road/Hillcrest Avenue construction project Nipsco energized the lift station today, so the department is able to begin connecting homes and businesses to the new lift station.

     Trustees Greenlee and Cook moved and seconded to allow the salaried payroll for September 1-15, 2006 and the claims for September 25, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Cook and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:22 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
GaryCook, President
Sanitary Board of Trustees

362
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, OCTOBER 9, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, October 9, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:19 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on September 25, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented the following report for September 2006:

Plant Operations:
1) Total flow in gallons                       58,534,752
2) Average daily flow in gallons          1,951,158
3) Monthly average in BOD removal          99.3%
4) Monthly average in TSS removal           97.2%
5) Monthly average in Ammonia removal 98.7%
6) Influent and effluent flow meters calibrated with telemetry on 9-26-2006.
7) Completed employee evaluations.
8) Replaced flow control valves on aerobic digesters.

Meetings Attended
9/11/06 Sanitary Board Meeting
9/18/06 Street bid opening
9/25/06 Sanitary Board Meeting
9/28/06 Flow meter start-ups for the Pretty Lake Conservancy District.
9/29/06 Pre-construction meeting with Rieth-Riley on street projects.

Collection System:
1) Cleaned 2,313 linear feet of sewer lines.
  • .0 during service calls
  • 2,313' during preventive mainentance
2) Televised 275 linear feet of sewer lines
3) Mechanically removed roots from 0 linear feet of sewer lines.
4) Removed approximately 0 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 4,500 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 13 pumping stations.
7) Continuing with the cleaning & inspection of the city owned sanitary sewer system, in accordance to the submitted CSO-L TCP. The trunk line on Polk St. is currently being cleaned along with both river siphons at the Magnetic Park and Cleveland St.
8) Replaced inlets:
     2 - at the 100 block of W. Jackson St.
     1 - at the intersection of Pennsylvania Ave. and Earl St.
     1 - at the intersection of LaPorte St. and Center St.
9) Repaired one existing inlet on Baker St.
10) Adjusted one manhole casting on Baker St
11) Completed replacing 2 sanitary manholes and 322' of main line in the 700 block of Pennsylvania Ave.

     Superintendent Davidson reported that Pennsylvania Avenue has been paved and the project is complete.

     Davidson said the final inspection on the Oak Road/Hillcrest Avenue pump station has taken place; everything is operational and four of the homes on the old line will be converted to the new station in the next couple of weeks.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for September 16-30, 2006 and the claims for October 9, 2006 as entered in Claim Register #2006. The motion carried.

     Mark Sullivan, Commonwealth Engineers, presented Contract Change Order No. 1 for the Oak Road Sanitary Sewer Extensions

Description of Changes Decrease
In Contract Price
Increase
In Contract Price
1. Raise Lift Station Grade to be even with Oak Rd. $ 1,625.00
2. Remove bad soil from beneath Wet Well and
     Valve pit and replace with stone base
$ 1,189.00
3. As-built quantities adjustment $ 1,630.50

363
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, OCTOBER 9, 2006

Totals $ 1,630.50 $ 2,814.00
Net Change in Contract Price       
$1,183.50

Justification
1. The Original design plans showed the top of the Oak Rd. Lift Station approximately 1.5 feet lower than the existing elevation of Oak Rd. This created a slight downhill grade from the road to the lift station. During winter months, this may have made access tricky. The station elevation was raised 1.5 feet to match the road. Additional backfill material was required to raise the grade. The net result was an increase in contract cost of $1,625.00

2. During excavation of the new wet well and valve pit, unstable soil was discovered. This soil was very wet and organic and not suitable to set the structures upon. The unsuitable material was removed and additional stone base material was added to make a stable base. The net result was an increase in contract cost of $1,189.00.

3. As-built quantities adjustment Final as-built quantities resulted in a project cost savings of $1,630.60.

     Trustees Benczik and Greenlee moved and seconded to approve the change order as submitted. The motion carried.

     Sullivan then presented a proposed Certificate of Substantial Completion on the Oak Road Sanitary Sewer Extension Project for Beer & Slabaugh, Inc. Sullivan said that there are items that need to be taken care of on the punch list. Sullivan said that the contractor has currently been paid in full except for the retainage, which is approximately $6,800.00. Sullivan said that the retainage amount is more than sufficient to pay for the items on the punch list. Sullivan said that the contractor told him he would be here next week to take care of the punch list items. Sullivan said that after that is done, Superintendent Davidson will recommend releasing the retainage. Sullivan recommended that the board consider issuing a Certificate of Substantial Completion to Beer & Slabaugh, Inc. as of October 9, 2006.

     Trustees Benczik and Greenlee moved and seconded to approve the request to issue a certificate of substantial completion effective October 9, 2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:15 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

364
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, OCTOBER 23, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, October 23, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:10 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Superintendent Donnie Davidson, Assistant Superintendent Larry Hatcher, Director of Public Works Rick Gaul and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on October 9, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for October 1-15, 2006 and the claims for October 23, 2006 as entered in Claim Register #2006. The motion carried.

     Pam Guard, 722 N. Michigan Street, reviewed the following information with the board:

September 25,2006

To Whom It May Concern:

When we purchased our home on March 31, 2004 it was divided into 3 rental units.

As of September 1, 2006 we have eliminated one of the rental units. Therefore, my family lives in one unit and I have 1 renter, making this a 2 unit home.

Please adjust our water, waste water and trash bill to reflect the change.

     Guard said that from April 2004 until August 2005 she was charged for four units.

     Trustee Benczik asked how that is charged and asked Building Commissioner Emmons if he would check to verify the number of units at the building.

     Clerk-Treasurer Hutchings said that there is a base fee per unit for the wastewater.

     Building Commissioner said that he was notified in September 2006 that Guard wanted him to inspect the residence, because the city office cannot change the billing until verification takes place. Emmons said that on September 25, 2006 he did verify that there are two apartments.

     Guard said that her bill has not been revised. She asked that her information be updated to show two units at 722 N. Michigan as of September 1, 2006.

     Cook asked if she was asking for everything to be placed to two units for that address at the present time.

     Guard replied, "Yes."

     Cook moved to show that the bills reflect the billing of two units at 722 N. Michigan Street effective September 23, 2006.

     Guard asked if they would be able to revise it.

     Hutchings said that the letter was dated September 25, 2006, so Mrs. Guard was billed for September usage at the previous number of units. The bill for October's usage will reflect two units.

     Cook modified his motion to change the billing to be for two units at 722 N. Michigan Street to be effective the date of Guard's letter, September 25, 2006. Trustee Benczik seconded the motion. The motion carried.

     Hutchings stated that the next billing, for October 2006, would be sent around November 20th. She verified with the board that the bill that was sent in October 2006 stands as billed. Cook verified that.

     Hutchings noted that she had also received the following letter from Dennis Emmons:

To Whom It May Concern
At the Plymouth Water Department

The property located at 1016 N. Michigan St., Plymouth, Indiana 46563 is not a duplex. Please make the necessary changes to your records.

365
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, OCTOBER 23, 2006

S/ Dennis Emmons, Building Commissioner                                                         Dated: 9/25/06

cc: Mayor Gary Cook
      Pam Sarber, RE/MAX Oak Crest Realty

     Mark Sullivan spoke regarding the Hoham Drive Sewer Project and the Oak Road Sewer Project. Sullivan presented a summary of the engineering money that was spent on the job. Sullivan requested that the city transfer some money within the budgets, but it will not make the price go up. He asked to increase the bidding and construction engineering budgets for the Oak Road Sewer Project.

October 23, 2006

City of Plymouth
Sanitary Board of Trustees
City Hall
124 North Michigan Street
Plymouth, Indiana 46563

Attn: Mr. Gary Cook, Mayor

RE: Engineering Amendment
        Hillcrest / Oak Road Sewer Contract

Gentlemen:

This is to request an increase to the Bidding and Construction Engineering budgets for the above noted project. The amounts of the increase are shown below. Additionally, you can see from the table below, the overall project costs are under budget.

Project Budgets
Hoham Sewer Oak Road Sewer
Contract Spent Contract Spent Increase
Bidding $4,500.00 $3,407.07 $4,500.00 $8,048.91 ($3,548.91)
Construction
Engineering
4,000.00 1,249.31 6,000.00 8,825.42 (2,825.42)
Inspection 15,000.00 4,545.77 25,000.00 13,697.88
Totals: $23,500.00 $9,202.15 $35,500.00 $30,572.21
Balances: $14,297.85 $4,927.79
 
The reason for the need to increase the budget is due to the project being quoted three (3) times during different time frames. The increase in Construction Engineering was again affected by the project being built in two phases, the changing of the lift station location design from the school property to the Felix property and the resulting land acquisition.

If this increase is acceptable to the Board, please indicate as much by signing this letter below.

     Trustees Benczik and Greenlee moved and seconded to approve the amendment as proposed. The motion carried.

     Guard asked if she would be reimbursed for the sixteen months that she was overcharged, beginning April 2004, and said that is what she is asking for.

     Cook said that his motion did not allow for reimbursement. Cook said that he could check into it and call her.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:23 p.m.

Toni l. Hutchings, lAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

366
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, November 13, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:07 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Director of Public Works Rick Gaul and Secretary Hutchings were also present. Superintendent Donnie Davidson was out of town at a seminar.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on October 23, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     The following report was submitted for October 2006:

Plant Operations:
1) Total flow in gallons                       60,091,384
2) Average daily flow in gallons          1,938,432
3) Monthly average in BOD removal          99.3%
4) Monthly average in TSS removal           97.0%
5) Monthly average in Ammonia removal 96.9%
6) Influent and effluent flow meters calibrated with telemetry on 10-24-2006.
7) Land applied 1,613,400 gallons (185.6 dry tons) of biosolids to local farm field, which is utilized for the fertilizer use.
8) IDEM's James Weingart visited our facility on 10-2 to inform us of the technical assistance his agency has to offer at no charge to the community.
9) Rebuilt 3 - 2" non potable hydrants.
10) Repaired flush lines on scum collection equipment to both primary clarifiers.
11) Laborer Jason Wallace took his IDEM Class 2 Municipal Wastewater exam on 10-12 in Elkhart, IN.
12) Winterized all equipment and operations at the wastewater facility.
13) On 10-17 Mark Styers, Gibson Insurance Co. performed a facility safety inspection. Several minor areas were suggested for modifications. All items the on the list have been addressed.

Meetings Attended
1019/06 Sanitary Board Meeting
10/23/06 Sanitary Board Meeting
10/24/06 "Addressing Storm Water Issues" conducted at the Swan Lake Resort in Plymouth, provided by IACT Municipal Management Institute.

Collection System:
1) Cleaned 3,095 linear feet of sewer lines.
  • 1,710' during service calls
  • 1,385' during preventive maintenance
2) Televised 4,379 linear feet of sewer lines
3) Mechanically removed roots from 3300 linear feet of sewer lines.
4) Removed approximately 10 tons of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 31,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 15 pumping stations.
7) Completed asphalt paving after sanitary sewer project in the 700 block of Pennsylvania Ave.
8) Installed 20 benchmarks in the central part of the city.
9) Received start-up training and performed the site inspection on the new lift station and sewer extension project located in the Oak Rd / Hillcrest Ave. area on 10-4.
10) All punch list items were completed on the above referenced project on 10-30.
11) 4 homes were removed from existing sewers and reconnected to the sanitary sewer on the above project.
12) The Pretty Lake Conservancy District went on line 10-20-2006. The City is now receiving wastewater from the district as homes connect to the new system.

     Director of Public Works Rick Gaul reviewed the following information with the board:

November 7,2006
Sanitary Board,

Mr. & Mrs. William Emery of 14680 Candie Lane and Mr. & Mrs. Donald Massing of 14678 Candie Lane requested to connect to the City of Plymouth collection system. The initial request was in early March of 2006 and the City has required the Emery's & Massing's to follow our current policy, which was adopted 6-13-2005.

The request is again very unique since the two owners share a condominium and is part of a condominium association, which has limited authority on land use. The condominium is not contiguous to the City's boundaries however the Condominium Association's property is contiguous to current boundaries.

Mr. Emery has attempted to follow the policy as closely as possible, which are displayed in the policy checklist below.
    • Formal request for annexation - attachment A.

367
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13,2006

    • Request for annexation was denied on 6-12-06 by the City of Plymouth Common Council.
    • Hardship request 6-26-06 for reasons of environmental impact - attachment B.
    • Documented environmental conditions - attachment B.
    • County Board of Health opinion - attachment B.
    • Engineer evaluation - attachment C & D.
    • Main line gravity sewer is not an option due to inadequate slope from the property to the existing city owned main.

The Emery's and Massing's appear to have provided the necessary documentation, which indicates that for the long term environmental well being of their property and adjacent properties, the best solution would be to connect to the City's collection system. The main difference in this request and previous requests is that this request is dealing with a failed system and recent denied requests were expansion related.

If the request is approved it is strongly recommended that if there are future requests from within the condominium association, the City denies these requests for individual systems. Based upon information received, it is possible there are septic system issues throughout the immediate area, which are either being ignored or have not fully developed.

Residents in the condominium association have turned down the request for annexation and the services provided, so if additional requests are presented the requests should be directed toward annexation, which would also include the Emery's and Massing's This would provide the collection of wastewater in a centralized system which meets City standards and eliminate undesired individual lines.

If approved, the contract with the Emery's and Massing's should be consistent with the contract the City currently has with the Pretty lake Conservancy District which includes approval to annexation which follows the property and additional language that would be appropriate for an individual residential connection.

S/ Donnie Davidson, Superintendent
City of Plymouth Wastewater Department

Attachment A

Request for Annexation

Honorable Gary L. Cook
Mayor, City of Plymouth                                                                                              May 4, 2006

We the undersigned are hereby making a formal request for annexation to the City of Plymouth. The purpose of this request is to allow for us, as customers living outside the city limits, to connect to the Plymouth Municipal Wastewater Utility.

Our house is a single structure divided into two living units (condominiums). We have separate addresses of 14678 (Massing) & 14680 (Emery) Candie lane, Plymouth, IN 46563. We have a single well & septic system which are shared by both units. In the past year we have had to have the septic system pumped out twice due to a system failure.

We have been advised by Stone Construction and the Health Department that getting connected to the Plymouth Utility is our only viable option. They have indicated that replacement of the existing septic system, in its present location, would not change our problem. We don't have any other place, on our property, to put a new system. Also, we are landlocked and there is no nearby available property, to purchase, for the establishment of a new system.

Please see the attached documentation in support of this request.

Thank you for your time and consideration.

Sincerely,
S/ Donald D. Massing                                                                                  S/ William H. Emery

S/Marjorie A. Massing                                                                                  S/Janet H. Emery
14678 Candie Lane                                                                                     14680 Candie Lane
Plymouth, IN 46563                                                                                      Plymouth, IN 46563


Annexation Survey Summary
Properties Surveyed For Against
Acorn Drive 8 7 0 7
Candie Lane 11 10 4 6
Totals 19 17 4 13

368
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13,2006

ANNEXATION SURVEY

At this time, would you be in favor of annexation into the city of Plymouth?

YES                                                                                                          NO     
1 - S/ William Emery                                                                 1 - S/Don Towle
14680 Candie Lane                                                                 14711 Acorn Drive

2 - S/ Virginia Bullock                                                               2 - S/ Beverly Lilley
14699 Candie Lane                                                                 14730 Candie Lane
                                                                                                                   Plymouth, IN

3 - S/Donald Massing                                                               3 - S/Ann Fetzer
14678 Candie Lane                                                                  14697 Candie Lane

4 - S/ Mary Lou McCarthy                                                          4 - S/ James R. Snyder
14704 Candie Lane                                                                 14729 Candie Lane

                                                                                                                    5 - S/ Mr. & Mrs. R. Benefil
                                                                                                                    14659 Candie Lane
                                                                                                                    Plymouth, IN 46563

                                                                                                                    6 - S/ Phyllis N. Burris
                                                                                                                    14702 Candie Lane
                                                                                                                    Plymouth, IN 46563

                                                                                                                     7 - S/ Jane Mannon
                                                                                                                     14710 Acorn Drive
                                                                                                                     (No but didn't wish to sign)

ANNEXATION SURVEY

At this time, would you be in favor of annexation into the city of Plymouth?

YES                                                                                                               NO
                                                                                                                       8 - S/ Shirley Harner
                                                                                                                       14652 Candie Lane

                                                                                                                       9 -S/ Chester Sroka
                                                                                                                       14671 Acorn Drive

                                                                                                                       10 - Hedwig Wiers
                                                                                                                       14672 Acorn Dr

                                                                                                                       11 - Bonita Gehring
                                                                                                                       14673 Acorn Dr

                                                                                                                       12 - Nancy Bannon
                                                                                                                       14713 Acorn Dr

                                                                                                                       13 - Slavica Stoyanovich
                                                                                                                       14712 Acorn Dr

Mayor Gary Cook
Plymouth, IN 46563                                                                                                                                     June 16, 2006

As per Councilman Garner's request, I located and contacted, by phone, the owners of the 20 acre field located south & east of the Tall Oak subdivision. They are Harold & Anna Mae Gay, 12854 Northants Circle, Carmel, IN 46032 (317-575-9344).

Mr. Gay passed away 3 months ago and Mrs. Gay has since been diagnosed with cancer. Because of her present personal situation and the subsequent tax increase on the property, she stated that she is not interested in being annexed in to the city.

She also stated that C & T Construction (Schoff brothers) have a first option on buying the property.

Sincerely submitted,

S/ William H. Emery
14680 Candie Lane
Plymouth, IN 46563

cc: Don & Marge Massing
self

369
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13, 2006

October 17, 2006

The septic system which services the home at 14678 & 14680 Candie lane is failing. There is no space on the properties for installation of a new system. The home owners, Don & Marge Massing and Bill & Jan Emery, are petitioning the city of Plymouth for an emergency hook-up to their sewer system. Prior to acting on their petition, the city would like to know if it would be possible to place a leech field in any of the common grounds of the association.

We the board members of the Tall Oaks Condominium Association deny the use of common grounds for this purpose because none of the areas in question are appropriate for this type of use due to the following:

1) Some already contain leech fields.
2) Some contain wells.
3) Some have soil (clay) not conducive for a field.

S/Nancy Bannon                                                                                                             S/Chester Sroka
President                                                                                                                          Board Member                                         
S/Beverly Lilley                                                                                                                 S/Heddy Wiers
Treasurer                                                                                                                          Board Member

S/ Pam Thomas                                                                                                              S/Jan Emery
Secretary                                                                                                                           Board Member

(the following is taken from the minutes of the Common Council meeting of June 12, 2006)

Don and Marjorie Massing, 14678 Candie lane and Bill and Jan Emery, 14680 Candie Lane, were present regarding their request for annexation as presented at the May 22nd council meeting.

At the May 22nd council meeting the council asked the petitioners to survey their neighbors to determine their wishes regarding annexation. Out of nineteen properties, seventeen were surveyed, with four property owners being in favor of annexation and thirteen property owners against annexation.

Councilmen Ripley and Greenlee moved and seconded to deny the request because the land is not contiguous to the City of Plymouth and it cannot become contiguous because there are not enough adjoining land owners in favor of the annexation to make the property contiguous. The motion carried. This will allow them to pursue the other steps of the policy.

Attachment B

Marshall County Health Dept.
Marshall County Building
112 W. Jefferson Street, Room 103
Plymouth, IN 46563
May 11, 2006
Mr. William Emery
14680 Candie Lane
Plymouth, IN 46563



Dear Mr. Emery:

You and Mr. Massing own a duplex at 14680 and 14678 Candie lane. You stated the septic is starting to fail and you provided two reports from Creed Septic Systems Specialist. Creed pumped the septic tank on Jan. 4, 2005 and on Oct. 13, 2005; both times Creed noted a failed system. In October he further stated that he was getting 'a lot of run back'.

You had Mr. Stone out to evaluate the property for a repair and he recommended hooking to city sewer if possible. The City of Plymouth has asked for a statement by this department on the repair options. While this department would try a repair over condemning the property, a repair permit would note the property has severe limitation for a septic system that makes it function questionable and if possible a sewer or other off lot system should be found. My recommendation is to hook to sewer.

The current system is behind the duplex. From the beginning things did not go according to plan. The septic permit was issued in 1986 for a trench system sized at 1480 square feet and restricted to the back of the lot. The permit had to be modified, a note on the permit indicates a 70 foot set back (front) reduced the space for the septic system. The system was changed to a bed of 2225 square feet. Beds are more compact, however one loses the sidewall area of the trenches and to compensate beds are typically increased in size by half. All available space in the back was used.

The lack of space is a major limitation for a repair. The property is approximately 136 by 132 feet. With the set backs from buildings and property lines about 21 feet of usable space is behind the duplexes. The sides have less space probably around 5 to 10 feet. The front has a bit more space however the well isolation distance takes out almost all of the space. Even if the well is moved the two driveways in front chop up the space too much to install an adequate system; the front was also deemed unsuitable on the 1986 permit.

The 1986 permit was for two (two-bedroom) units, current GIS information indicates they are two (three-bedroom) units. Septics are sized by the number of bedrooms and a larger system with a pump should now be installed. Using the 186 sizing (probably outdated) the current

370
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13, 2006

system would ideally be 2220 square feet of trench or 3330 square feet of bed. It is unlikely this would fit on the property.

The current system is barely meeting the isolation distance from the building and property line. A new system in this area would have to go back in the same spot in which the soil is not adequately accepting the effluent. Proper septic design would be to avoid using the same area that the failed system is occupying.

Surface water run off is another problem. The septic are is sandwiched between the buildings and higher ground to the north and west. Water runs off the higher ground and hits the relatively level ground of the septic area before moving off to the east. During and after a rain event surface water is being directed on the septic area. The septic area is in effect doing double duty trying to take the water from the dwellings plus additional load of surface water. This water combination is a significant hardship on any septic and good practice would be to avoid such an area.

While some alternatives system might have a slight advantage in one area or another the net result would not significantly improve the outcome. Lack of space, surface run off, and being placed in the same area as the failing system, would be just as likely to adversely affect an alternative system as a it would a conventional system.

In my opinion this lot has significant limitations for a septic that can not adequately overcome by any septic systems. My recommendation would be to hook to a sewer if available.

Sincerely,
S/ Wesley Burden
MCHD Administrator

CC: Mr. Donald Massing
        14678 Candie Lane
        Plymouth, IN 46563


Attachment C

Strang & Associates
Consulting Engineers
703 Dickman Street
Plymouth, IN 46563

10/4/06

Bill Emery
14680 Tall Oaks Estates
Plymouth, IN 46563

Dear Mr. Emery,

I am responding to your request for options regarding sewage disposal for you and Don Massing. It is my understanding that you both share the same septic system as a duplex. It is my opinion that an onsite sewage disposal system is not feasible for your lot based on my visit to the site on 10/2/06. Your current septic disposal system located in the back yard is undersized. Runoff from the neighboring lots to the West and North are further complicating the problem and causing the system to fail. No more back yard space is available as the current system takes up the entire back yard. Based on our experience dealing with technologies such as drip irrigation systems, infiltrators, mound septic systems, and conventional systems, the front yard is too small to place an adequately sized system. At this time, no long term onsite solution is available.

There are only three other options; Pump and Haul, Offsite treatment, and Tying into the City Sewer. Pump and haul is not an economical long term solution. Pumping sewage to a purchased offsite property would not be economical either. The only viable option is to tap into the City of Plymouth's Sewer. There is more than one way to do this by either going down the back property line or the Front Road Right of Way. You have two potential ways of piping, by gravity sewer or pump and pressurized piping. Field work will be needed to verify the feasibility of a gravity sewer lateral. I recommend having a design professional familiar with these types of construction design either system. I also recommend doing a cost analysis to find the best option.

If you have any questions, concerns, or require more information please contact us at your convenience.

Sincerely,
S/Dan Sellers P.E.


Attachment D

Strang & Associates
Consulting Engineers
703 Dickman Street
Plymouth, IN 46563

10/19/06

371
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 13, 2006

Plymouth Wastewater Dept
Attn: Donnie Davidson
900 Oakhill Avenue
Plymouth, IN 46563

Dear Mr. Davidson,

On behalf of Mr. Bill Emery of Candie lane, I am submitting some additional information concerning his request for emergency hookup to City sewer. After investigating the ground owned by the Tall Oaks Condominium Association, a properly sized leach field for the Condo units owned by Mr. Emery and Don Massing will not physically fit into any ground owned by the Association. Limiting factors are 50' setbacks from existing wells, evidence of disturbed soil, and records of existing leach fields. The Condo Association has also denied Emery's request to use the common grounds as an offsite means of sewage disposal.

The only ground that is physically fit for a drainage leach field is the farm field to the east. This field remains unavailable to Mr. Emery as it has a condition of First Right to Buy by another entity. Pump and Haul is not a long term solution accepted by the State. Connecting to the city sewer is now Emery's only option.

I have advised Mr. Emery that he must design such a hookup to the sewer conducive to the annexation of his and other properties. He also understands that he cannot contest annexation.

If you require further information to have additional concerns please contact me as you are able.

Sincerely,
S/ Dan Sellers P. E.

CC: Bill Emery

     Trustee Benczik asked if the Emerys and Massings had received this letter.

     They replied that they had not received a copy of the letter.

     Benczik asked them if they are aware of any other properties that are having problems with septic systems at this time.

     Mr. Emery said that he has heard talk, but officially is not aware of any more homes with problems at this time.

     Benczik said that even if the city approves the request, there are inspections and agreements that would need to be completed.

     Trustees Greenlee and Benczik moved and seconded to approve the request for service. The motion carried.

     Trustees Cook and Benczik moved and seconded that if there is another situation that arises based upon environmental issues, those properties will be required to be annexed and the system will need to be sized large enough to accommodate the whole condominium association. The motion carried.

     Benczik asked that the condominium association board members receive individual notice (board minutes) informing them of this stipulation.

     Hutchings agreed to send the minutes to the condominium board members.

     City Attorney Simanski said he would prepare the contract.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for October 16-31, 2006 and the claims for November 13, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:26 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

372
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, NOVEMBER 27, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, November 27, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:07 p.m.

     Mayor Gary Cook presided for Trustees Greenlee and Benczik. City Attorney Simanski, Director of Public Works Rick Gaul, Superintendent Donnie Davidson and Secretary Hutchings were also present.

     Trustees Benczik and Greenlee moved and seconded to approve the minutes of the last regular meeting on November 13, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Donnie Davidson reported that the Pretty Lake Conservancy District has been connected to the city's system. To date, there are seventeen homes connected to the system, there are 103 more connections that have to be made by July 1st.

     Davidson said that he is gathering information for the Emery/Massing sewer connection agreement and should have that information to the city attorney later this week. Davidson said he would like to have the agreement for the board's consideration at the December 11th meeting.

     Trustees Greenlee and Benczik moved and seconded to allow the salaried payroll for November 1-15, 2006 and the claims for November 27, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:10 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

373
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, DECEMBER 11, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Monday, December 11, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of  the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at 6:05 p.m.

     Mayor Gary Cook presided for Trustee Benczik. City Attorney Simanski, Director of Public Works Rick Gaul, Superintendent Donnie Davidson and Secretary Hutchings were also present. Trustee Greenlee was absent.

     Trustees Benczik and Cook moved and seconded to approve the minutes of the last regular meeting on November 27, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     The following report was submitted for November 2006:

Plant Operations:
1) Total flow in gallons                        54,926,856
2) Average daily flow in gallons           1,830,895
3) Monthly average in BOD removal          99.3%
4) Monthly average in TSS removal           97.1%
5) Monthly average in Ammonia removal 99.2%
6) IDEM inspection of the plant and collection system by Mark Kuss on 11-14 and 11-15.
7) Relocated the Department of Public Works to the Wastewater Facility.
8) Received 3 awards at the 2006 Indiana Water Environmental Annual Conference
    • Biosolids Award (Operating Projects)
    • Laboratory Excellence
    • Safety Excellence
9) Preventive Maintenance Program - Electrical testing of all plant and lift station motors, wiring and motor control centers.

Meetings Attended
11/13-11/14/06 2 men attended the Indiana Water Environment Annual Conference
11/15/06 3 men attended the Indiana Water Environment Annual Conference
11/27/06 Sanitary Board Meeting

Collection System:
1) Cleaned 3,535 linear feet of sewer lines.
  • 1,893' during service calls
  • 1,642' during preventive maintenance
2) Televised 353 linear feet of sewer lines
3) Mechanically removed roots from 651 linear feet of sewer lines.
4) Removed approximately 1 ton of silt and debris during cleaning and inspections of sanitary sewers.
5) Used approximately 10,000 gallons of potable water during sewer cleaning.
6) Performed routine maintenance on 10 CSO and 15 pumping stations.
7) The Pretty Lake Conservancy District went on line 10-20-2006. The City is now receiving wastewater from the district as homes connect to the new system. As of 11-30-2006, 16 homes have been connected.
8) Mapping, inspecting and generating elevations of all utility structures in the southern part of the city. This information will be used for modeling the city's CSO and Stormwater flows by incorporating the information into the city's GIS.

     Superintendent Donnie Davidson reported on the combined sewer overflow plan that has been submitted and reviewed by IDEM. Davidson said that the public comment period ended about two weeks ago so he hopes to have that information from IDEM by the end of the year. He will then solicit proposals for engineering work on the treatment plant, provided it was accepted as presented.

     Trustees Cook and Benczik moved and seconded to allow the salaried payroll for November 16-30, 2006 and the claims for December 11, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Benczik and Cook moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:07 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees

374
REGULAR SESSION, SANITARY BOARD OF TRUSTEES, DECEMBER 27, 2006

     The Sanitary Board of Trustees of Plymouth, Indiana, met in regular session on Wednesday, December 27, 2006, immediately following the Water Works Board of Trustees meeting in the Council Chambers of the City Building, 124 N. Michigan Street, Plymouth, IN. The meeting was called to order at  6:11 p.m.

     Mayor Gary Cook presided for Trustee Greenlee. City Attorney Simanski, Director of Public Works Gaul, Superintendent Davidson and Secretary Hutchings were also present. Trustee Benczik was absent.

     Trustees Greenlee and Cook moved and seconded to approve the minutes of the last regular meeting on December 11, 2006, and to dispense with reading them since they have been reviewed and found to be correct, motion carried.

     Superintendent Davidson presented a draft copy of updated sewer standards to the board. Davidson said that it has been several years since the standards were updated and there have been updates in material use and installation techniques which need to be added to the standards. They are attempting to address the unique situations that have occurred over the years to provide consistency for the various requests. He asked for the members to review the draft and forward any comments to him.

     Davidson presented the following information to the board:

The City of Plymouth Wastewater Department is a member of the Northern Indiana Operators Association. The association is made up of Indiana Certified Wastewater Operators and Engineers. The purpose of the organization is to provide training to operators, regulatory updates, operator assistance, community networking and problem solving.

On December 13, 2006, Larry Hatcher received the Association's award for "Operator of the Year". The award recognizes an individual who has been nominated by his peers, who has demonstrated efforts within the field of Wastewater Treatment that have been outstanding and beneficial within the Association.

It is obvious the dedication Larry has provided the Wastewater Department and the City of Plymouth. I would like to personally thank Larry for his effort and concern in making Plymouth a model community.

     Davidson noted that Hatcher attends the Sanitary Board of Trustees meetings on his own time in an attempt to continue learning.

     City Attorney Simanski referred to a draft Agreement for Extension of Sewer Line and Waiver of Future Objections to Annexation. He asked that the board members, Superintendent Davidson and Clerk-Treasurer Hutchings review the draft and forward any comments to him, at which time he will update the draft and forward it to Mr. & Mrs. Emery and Mr. and Mrs. Massing for their review.

     Superintendent Davidson said that there are concerns regarding billing procedures. There are proposed to be two different water meters at this location. But often in situations including condominiums and apartments, there is only one meter and that becomes a problem when one of the units does not pay their utility bill and it becomes an issue to disconnect service. Davidson reminded the board that situations like this could include a lot of administrative work by the City of Plymouth for property that is located outside the corporate limits. Davidson noted that one way to eliminate those potential problems is to deny all future requests for service outside of the city limits.

     Trustees Greenlee and Cook moved and seconded to allow the salaried payroll for December 1-15, 2006 and the claims for December 27, 2006 as entered in Claim Register #2006. The motion carried.

     There being no further business to discuss, Trustees Cook and Greenlee moved and seconded to adjourn the meeting. Motion carried. The meeting adjourned at 6:23 p.m.

Toni L. Hutchings, IAMC/CMC
Secretary and Finance Officer

APPROVED:
Gary Cook, President
Sanitary Board of Trustees